Construction Updates,May 2025

Check updates:
NeoSkiesNeoHills
NeoSquareNeoValley • NeoPark

Update as on 5th May, 2025

NeoSkies
100%
NeoHills
100%
NeoSquare
100%
NeoValley Kaveri A
34%
NeoValley Kaveri B
64%
NeoValley Narmada
32%
NeoPark - A
73%
NeoPark - B
67%

% mentioned above is the current demand due as per the construction linked payment schedule

NeoSkies – Sale building
OC Received
NeoSkies – Sale building

RCC work
Top RCC slab 100% completed.

Finishing work
Waterproofing work in progress ( 100% completed)
Conceal plumbing work in progress ( 100% completed)
Gypsum work 100% completed .
Flat flooring work 100% completed.
Door shutter work 99% completed.
Flat window work 99% completed.

NeoSkies – Rehab building

RCC work
OC received

Finishing work
177 flat possession handover

Infra
Sewage Treatment Plant &  Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.

NeoHills – Sale building
OC Received
NeoSquare – A wing

RCC work
RCC 100% work completed

Flat Finishing
Block work finalized till terrace floor
Electric concealed work completed & Electrical wiring work completed 100%
Gypsum plaster work 100% completed
Waterproofing & plumbing work completed till top floor
Flat tiling work & door frames work completed at 1st to 22nd floor
Lift lobby tiling work completed at 1st to 22nd floor
Main door frames making & fixing work completed till 22nd floor
External painting work completed

RCC Infra
UG water tank civil work completed &  domestic & fire tank work in progress.

NeoSquare – B wing 

OC Received
RCC work completed till top slab

Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed .
Staircase flooring is completed from ground floor to till terrace.
Electric duct FRD door are fixed.
Schindler lift installation completed.
External painting work completed & Internal painting work completed

NeoSquare – C wing

OC Received
RCC  completed till top slab

Flat finishing
Kitchen extension work completed till top floor
Concealed plumbing & waterproofing is completed.
Electrical conducting work completed
Terrace waterproofing work completed .

Common area finishing
Completed

NeoValley  ( Kaveri ) – Sale building  B 

Excavation, Foundation & Base Work – Excavation, PCC, Footing work 100% completed .
Structural Progress – RCC slab for the 15th floor has been completed.

NeoValley  ( Kaveri ) – Sale building A

Foundation Work – Excavation and footing work are 100% completed.
Plinth work is also fully done, forming a solid base for the structure.
Structural Progress – RCC slab work from the 1st to 3rd floors is completed & 4th floor slab work is currently in progress

NeoValley ( Kaveri ) – Rehab building ( Sahjeevan )

RCC work
RCC work completed till top slab

Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover

NeoValley  ( Narmada ) – Sale building C

construction not commenced yet

NeoValley  ( Narmada ) – Sale building B

Excavation Work– Foundation & Excavation work 100% completed & plinth 80 % completed

NeoValley  ( Narmada ) – Rehab building A

Foundation & Base Work -Foundation and plinth work are now 100% completed, providing a strong and stable base for the building.
Structural Progress – RCC slab work from the 1st to the 4th floor is fully completed. 5th floor slab work is currently 50% completed and progressing smoothly.

NeoPark – Rehab Building D wing


Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 21st floor is fully completed.
Finishing– Blockwork is completed up to the 19th floor , Gypsum plastering is completed up to the 18th floor.

NeoPark – Sales building A wing


Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 22nd floor is fully completed.
Finishing– Blockwork is completed up to the 20th floor , Gypsum plastering is completed up to the 18th floor.

NeoPark – Sales building B wing


Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 22nd floor is fully completed.

NeoPark – Sales building C wing


Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st & 2nd floor is 50% completed.

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work completed till 20th slab & 21st floor slab 5% completed
Finishing work Blockwork completed till 15th floor
Plumbing Conceal work completed upto 15th floor
Gypsum work completed upto 14th floor
Water proofing completed upto 11th floor
Flat flooring completed upto 4th floor
Infra STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed.
NeoSkies – Sale building RCC work Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% .
NeoHills – Rehab building RCC work Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress.
NeoHills – Sale building RCC work Substructure work 100% completed
Superstructure 1st floor slab in progress.
NeoSquare – A wing RCC work 2nd Slab completed
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor)
Common area finishing Gypsum on some of the floors completed
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 10th floor level
Chajja casting completed.
Flat finishing Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed
Common area finishing Completed
Services Services of extra flat(PAP unit flat No 7) is pending rest is completed

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.