% mentioned above is the current demand due as per the construction linked payment schedule
NeoSkies – Sale building
OC Received
NeoSkies – Sale building
RCC work
Top RCC slab 100% completed.
Finishing work
Waterproofing work in progress ( 100% completed)
Conceal plumbing work in progress ( 100% completed)
Gypsum work 100% completed .
Flat flooring work 100% completed.
Door shutter work 99% completed.
Flat window work 99% completed.
NeoSkies – Rehab building
RCC work
OC received
Finishing work
177 flat possession handover
Infra
Sewage Treatment Plant & Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.
NeoHills – Sale building
OC Received
NeoSquare – A wing
RCC work
RCC 100% work completed
Flat Finishing
Block work finalized till terrace floor
Electric concealed work completed & Electrical wiring work completed 100%
Gypsum plaster work 95% completed
Waterproofing & plumbing work completed till top floor
Flat tiling work & door frames work completed at 2nd to 22nd floor & 1st floor in progress
Lift lobby tiling work completed at 2nd to 22nd floor
Main door frames making & fixing work completed till 22nd floor
External painting work completed
RCC Infra
UG water tank civil work completed & domestic & fire tank work in progress.
NeoSquare – B wing
RCC work completed till top slab.
Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed .
Staircase flooring is completed from ground floor to till terrace.
Electric duct FRD door are fixed.
Schindler lift installation completed.
External painting work completed & Internal painting work in progress.( 90% completed)
NeoSquare – C wing
RCC work
RCC completed till top slab
Flat finishing
Kitchen extension work completed till top floor
Concealed plumbing & waterproofing is completed.
Electrical conducting work completed
Terrace waterproofing work completed .
Common area finishing
Completed
NeoValley ( Kaveri ) – Sale building B
Excavation work 100% completed .
PCC work 100% completed.
Footing work 100% completed.
Foundation & plinth work completed.
9th slab work completed
NeoValley ( Kaveri ) – Sale building A
Excavation & footing work 100% completed .
Part plinth work completed
NeoValley ( Kaveri ) – Rehab building ( Sahjeevan )
RCC work
RCC work completed till top slab
Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover
NeoValley ( Narmada ) – Sale building C
construction not commenced yet
NeoValley ( Narmada ) – Sale building B
Excavation for non tower area work 75 % completed
Foundation & Excavation work in progress.
NeoValley ( Narmada ) – Rehab building A
Foundation work 100% completed.
plinth work 100 % completed)
NeoPark – Rehab Building D wing
RCC work
Plinth RCC work 100% completed.
21st slab work completed
Block work completed till 19th floor & Gypsum work completed till 15th floor .
NeoPark – Sales building A wing
RCC work
Piling work completed .
Substructure work in progress
Plinth work completed & 1st to 22nd slab work completed.
Block work completed till 13th floor & gypsum work completed till 6th floor
NeoPark – Sales building B wing
RCC work
Foundation work completed & substructure work in progress.
Plinth work completed.
RCC 11th slab work completed
NeoPark – Sales building C wing
RCC work
Excavation work 100% completed & Foundation work Completed
Substructure work completed 70 %
Tower | Floor Details | Detailed Updates |
---|---|---|
NeoSkies – Rehab building | RCC work | RCC work completed till 20th slab & 21st floor slab 5% completed |
Finishing work | Blockwork completed till 15th floor Plumbing Conceal work completed upto 15th floor Gypsum work completed upto 14th floor Water proofing completed upto 11th floor Flat flooring completed upto 4th floor |
|
Infra | STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed. | |
NeoSkies – Sale building | RCC work | Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% . |
NeoHills – Rehab building | RCC work | Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress. |
NeoHills – Sale building | RCC work | Substructure work 100% completed Superstructure 1st floor slab in progress. |
NeoSquare – A wing | RCC work | 2nd Slab completed |
NeoSquare – B wing | Ground to OHWT | RCC completed |
Flat Finishing | Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor) | |
Common area finishing | Gypsum on some of the floors completed | |
Services | Only fire fighting completed | |
NeoSquare – C wing | RCC | RCC of main building completed PAP unit – extension flat at 10th floor level Chajja casting completed. |
Flat finishing | Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed | |
Common area finishing | Completed | |
Services | Services of extra flat(PAP unit flat No 7) is pending rest is completed |