Construction Updates – December 2018
Construction Updates – December 2018
Emerald Tower completed till terrace Slab
The construction at Marathon Nextown is proceeding speedily. More than 50 families are already staying in the 3 completed towers. Emerald is completed till the terrace slab, Coral till 12th slab and the 1st slab is in progress for Sapphire. Please refer to the table below for detailed updates.
Emerald Tower completed till terrace Slab.
The construction at Marathon Nextown is proceeding speedily. More than 50 families are already staying in the 3 completed towers. Emerald is completed till the terrace slab, Coral till 12th slab and the 1st slab is in progress for Sapphire. Please refer to the table below for detailed updates.
Tower | Floor Details | Detailed Updates |
---|---|---|
Emerald | Completed work up to Terrace slab level | 90% RCC work completed. Parapet wall constructed. Finishing work completed till 7th Floor. Internal Civil work completed till the 18th floor. Waterproofing, plumbing, and tiling in progress from 7th floor onwards. External painting is In progress |
Coral | Completed work up to 12th slab level | 60% RCC work completed – 13th slab completed. Internal Civil work completed till 7th floor. Waterproofing, plumbing and tiling in progress from 2nd floor onwards. |
Sapphire | Initiated work for first slab level | 10% RCC work completed – 1st Slab in progress. |