Construction Updates – December 2018

Construction Updates – December 2018

Emerald Tower completed till terrace Slab

The construction at Marathon Nextown is proceeding speedily. More than 50 families are already staying in the 3 completed towers. Emerald is completed till the terrace slab, Coral till 12th slab and the 1st slab is in progress for Sapphire. Please refer to the table below for detailed updates.

Emerald Tower completed till terrace Slab.

The construction at Marathon Nextown is proceeding speedily. More than 50 families are already staying in the 3 completed towers. Emerald is completed till the terrace slab, Coral till 12th slab and the 1st slab is in progress for Sapphire. Please refer to the table below for detailed updates.

Tower Floor Details Detailed Updates
Emerald Completed work up to Terrace slab level 90% RCC work completed.
Parapet wall constructed.
Finishing work completed till 7th Floor.
Internal Civil work completed till the 18th floor.
Waterproofing, plumbing, and tiling in progress from 7th floor onwards.
External painting is In progress
Coral Completed work up to 12th slab level 60% RCC work completed – 13th slab completed.
Internal Civil work completed till 7th floor.
Waterproofing, plumbing and tiling in progress from 2nd floor onwards.
Sapphire Initiated work for first slab level 10% RCC work completed – 1st Slab in progress.
Get in touch

Site and Sales Office
Marathon Nextown,Opp. Padle Gaon Bus Stop,
Off Kalyan-Shil road, Thane.
Maharashtra 421204

T: 022 67248599 / 022 67728499

E: [email protected]

Whatsapp: 07738734222

Enquire Now
  • We respect your privacy
  • This field is for validation purposes and should be left unchanged.
Explore Nextown