Construction Updates – February 2025

Update as on 3rd February, 2025

Construction Updates – February 2025

Update as on 3rd February, 2025

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA & ELARA Great news! Aura and Elara towers have received Occupancy Certificate (OC) up to the 35th floor, meaning they are ready for possession.
Tower Updates
NOVA

(Under Construction – Significant Progress Made)

Structural Progress:

RCC framework is completed up to the 24th floor.

Interior Work:

Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor.

Plumbing & Waterproofing: Installed up to the 23rd floor.

Gypsum Work: Completed up to the 22nd floor, with work ongoing on the 23rd floor.

Kitchen Platforms: Installed up to the 22nd floor, with 23rd-floor work in progress.

Flooring: Tiling completed up to the 21st floor, and ongoing on the 22nd & 23rd floors.

Doors & Frames: Installed up to the 16th floor, with ongoing work on the 17th & 18th floors.

Fire Safety: Firefighting system work completed up to the 23rd floor.

External & Infrastructure Work:

Surrounding infrastructure work has begun.

Stormwater drainage is 75% complete.

Basement & underground facilities (such as water tanks and STP) are fully completed.

Tower Updates
NOVA

(Under Construction – Significant Progress Made)

Structural Progress:

RCC framework is completed up to the 24th floor.

Interior Work:

Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor.

Plumbing & Waterproofing: Installed up to the 23rd floor.

Gypsum Work: Completed up to the 22nd floor, with work ongoing on the 23rd floor.

Kitchen Platforms: Installed up to the 22nd floor, with 23rd-floor work in progress.

Flooring: Tiling completed up to the 21st floor, and ongoing on the 22nd & 23rd floors.

Doors & Frames: Installed up to the 16th floor, with ongoing work on the 17th & 18th floors.

Fire Safety: Firefighting system work completed up to the 23rd floor.

External & Infrastructure Work:

Surrounding infrastructure work has begun.

Stormwater drainage is 75% complete.

Basement & underground facilities (such as water tanks and STP) are fully completed.

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.