Construction Updates – February 2025
Update as on 3rd February, 2025
Construction Updates – February 2025
Update as on 3rd February, 2025
Tower | Updates |
---|---|
AURA & ELARA | Great news! Aura and Elara towers have received Occupancy Certificate (OC) up to the 35th floor, meaning they are ready for possession. |
Tower | Updates |
---|---|
NOVA |
(Under Construction – Significant Progress Made) |
Structural Progress:
RCC framework is completed up to the 24th floor. |
|
Interior Work:
Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor. Plumbing & Waterproofing: Installed up to the 23rd floor. Gypsum Work: Completed up to the 22nd floor, with work ongoing on the 23rd floor. Kitchen Platforms: Installed up to the 22nd floor, with 23rd-floor work in progress. Flooring: Tiling completed up to the 21st floor, and ongoing on the 22nd & 23rd floors. Doors & Frames: Installed up to the 16th floor, with ongoing work on the 17th & 18th floors. Fire Safety: Firefighting system work completed up to the 23rd floor. |
|
External & Infrastructure Work:
Surrounding infrastructure work has begun. Stormwater drainage is 75% complete. Basement & underground facilities (such as water tanks and STP) are fully completed. |
Tower | Updates |
---|---|
NOVA |
(Under Construction – Significant Progress Made) |
Structural Progress:
RCC framework is completed up to the 24th floor. |
|
Interior Work:
Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor. Plumbing & Waterproofing: Installed up to the 23rd floor. Gypsum Work: Completed up to the 22nd floor, with work ongoing on the 23rd floor. Kitchen Platforms: Installed up to the 22nd floor, with 23rd-floor work in progress. Flooring: Tiling completed up to the 21st floor, and ongoing on the 22nd & 23rd floors. Doors & Frames: Installed up to the 16th floor, with ongoing work on the 17th & 18th floors. Fire Safety: Firefighting system work completed up to the 23rd floor. |
|
External & Infrastructure Work:
Surrounding infrastructure work has begun. Stormwater drainage is 75% complete. Basement & underground facilities (such as water tanks and STP) are fully completed. |