Construction Updates – May 2025
Update as on 8th May, 2025
Construction Updates – May 2025
Update as on 8th May, 2025
Tower | Updates |
---|---|
AURA & ELARA | Aura and Elara towers have received Occupancy Certificate (OC) up to the 35th floor |
Tower | Updates |
---|---|
NOVA |
(Under Construction – Significant Progress Made) |
Structural Progress:
Slab work is completed up to the 24th floor. |
|
Interior Work:
Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor. Plumbing & Waterproofing: Installed up to the 23rd floor. Gypsum Work: Completed up to the 23rd floor. Kitchen Platforms: Installed up to the 23rd floor. Flooring: Tiling completed up to the 23rd floor. Doors & Frames: Installed up to the 23rd floor. Fire Safety: Firefighting system work completed up to the 23rd floor. |
|
External & Infrastructure Work:
Surrounding infrastructure work in Progress. Storm water drainage is 90% complete. Basement & underground facilities (such as water tanks and STP) are fully completed. |
Tower | Updates |
---|---|
FLORA |
(Under Construction – Significant Progress Made) |
Structural Progress:
Slab work is completed up to the 6th Floor & 7th floor RCC pour 1 completed and pour 2 will be in progress. |
|
External & Infrastructure Work:
Basement & underground facilities (such as water tanks and STP) are fully completed. Periphery Retaining Wall & Pump Room Construction completed. |