Construction Updates – September 2024

Update as on 11th September, 2024

Construction Updates – September 2024

Update as on 11th September, 2024

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

OC Received till 35th Floor

ELARA

OC Received till 35th Floor

NOVA

RCC 24th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Back filling Completed
Ground Floor Column Work Completed Till 24th Slab Work Completed.
OHT bottom slab work completed.
Block-work up to 23rd floor completed.
Plumbing Conceal Work up to 16th Floor Completed. 17th to 19th Floor Work in Progress.
Waterproofing up to 16th Floor Completed. 17th to 19th Floor Work in Progress.
Gypsum Work completed till 20th floors & 21st floor work in progress.
Kitchen platform work completed till 10th floor & 11th , 12th floor work in progress.
Tiling work completed till 9th floor , 10th & 11th floor work in progress.
Door frame fixing work completed till 4th floor & 5th & 6th floor work in progress.
Fire fighting work till 18th floor & 19th floor work in progress
Surrounding Infra Work Started
Storm Water Drainage 50% Completed

FLORA

Excavation Work Completed
Foundation (Raft) work completed.
Periphery – retaining wall work completed.
STP and UG tank civil work completed
Pump room wall casting completed
Plinth slab completed.
Ground floor column completed only lift column work in progress. pour 1 slab shuttering in progress