Construction Updates,
April 2025
Update as on 3rd April 2025
PHASE 1
ZENITH, ZODIAC, ACRUX, ALTIS, ATLAS, ATRIA, AURA, AVIOR, ION, VEGA, TRITON
ANTILIA
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On or before Possession
| 7% | Will be update soon |
Structure Work: The main RCC (concrete) structure of the building is now fully completed up to the terrace level.
Masonry & Flooring: All internal blockwork and flooring have been completed up to the 30th floor.
Wall Finishing: Gypsum and cement plastering work is done on all floors, ensuring smooth, finished walls ready for painting and interiors.
Railings & Fixtures: MS railings are fully installed for added safety. Work on polishing the main doors and finishing window frames is actively underway on multiple floors.
Waterproofing & Kitchens: Waterproofing and kitchen platform installations have been completed up to the 30th floor, preparing homes for the next stage of interiors.
Fire Safety: The entire firefighting system has been fully installed across the building to ensure your safety and peace of mind.
Exterior Look: External painting is 85% complete, giving the tower its final appearance and adding to the overall aesthetic.
Elevators: Lift installation work is 75% complete, and soon all floors will have smooth and convenient access.
PHASE 2
CEDAR
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On or before Possession
| 7% | will be updated soon |
Structure Work: RCC (concrete) structure is fully completed up to the 28th floor, including the main superstructure.
Walls, Flooring & Plastering: Internal blockwork, flooring, and plastering are finished up to the 27th floor, giving shape to the interiors of your future home.
Plumbing & Kitchens: Internal plumbing lines and kitchen platform installations are also complete up to the 27th floor.
Safety First: The entire firefighting system has been fully installed across the building to ensure your safety.
Elevators: Lift installation is 75% complete—soon, all floors will be easily accessible.
Exterior Painting: External painting is 100% finished, giving the building its final and polished look.
Terrace Waterproofing: Waterproofing work on the terrace is complete, protecting the structure for the long run.
DAFFODIL
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On or before Possession
| 7% | Will be updated soon |
Structure Completed: RCC work, including the full superstructure, is now 100% complete.
Walls & Plumbing: Blockwork is fully done from the 1st to the 27th floor. Concealed internal plumbing has also been completed up to the 27th floor.
Staircase Finishing: Staircase flooring is finished till the 27th floor, ensuring smooth and safe movement within the tower.
Safety Systems: Firefighting and alarm systems are fully installed across the building, prioritizing safety for all residents.
Waterproofing: Waterproofing work is completed up to the 27th floor, adding long-term protection and durability to the structure.
BODHI
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On Flat / Premises Completion
| 8% | 15/03/25 – 15/05/25 |
On possession
| 7% | Will be updated soon |
Structure Work: The superstructure RCC work, including the 28th floor slab and terrace slab, is now fully completed—along with the foundation and plinth slab.
Ground Floor Ready: All work on the ground floor is fully completed.
Flat Interiors: Flooring inside flats is completed up to the 27th floor, bringing the interiors closer to completion.
Walls & Plumbing: Blockwork is 100% done, and concealed plumbing is finished up to the 27th floor.
Wall Finishing: Gypsum plaster work has been completed till the 27th floor, giving walls a smooth and finished surface.
Doors: Door frame installation is done up to the 26th floor.
Fire Safety: Firefighting system installation is 100% complete, ensuring full building safety.
Lift Installation: Preparations for lift installation are underway to provide smooth access across all floors soon.
ASTER
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On or after initiation of Lift-Stair lobby,etc (E)
| 7% | 15/04/25 – 05/07/25 |
On or after initiation of Electrical / Painting of the flat / Premises
| 8% | 05/05/25 – 27/07/25 |
On Flat / Premises Completion | 3% | 30/07/25 |
On possession | 4% | Will be updated soon |
Structural Work: The RCC structure is fully completed up to the 28th floor, including the terrace slab—marking a major milestone.
Strong Foundations: Foundation, columns, and plinth work are fully done, providing a strong and reliable base for the building.
Lower Ground Progress: Backfilling and ground slab work up to the Lower Ground level are completed.
Wall Work: Blockwork is finished up to the 27th floor, forming the internal layout of the homes.
Flooring & Kitchens: Flat flooring and kitchen platform installations are currently in progress across multiple floors.
Wall Finishing: Gypsum plastering has been completed up to the 22nd floor, giving a smooth finish to walls.
Plumbing: Concealed plumbing work is fully completed up to the 27th floor.
Fire Safety: Installation of the firefighting system is 60% complete and progressing steadily.
% mentioned above is the current demand due as per the construction linked payment schedule. The timeline for upcoming milestone mentioned above is tentative & only provide to enable better cash flow planning for customers. Actual timelines may vary as per site conditions.










AMENTIES
Swimming pool work 100% completed.
Kids play area 100% work completed.
Clubhouse work in progress. ( 75% completed & functional )