Construction Updates,
April 2025

Update as on 3rd April 2025

PHASE 1

ZENITH, ZODIAC, ACRUX, ALTIS, ATLAS, ATRIA, AURA, AVIOR, ION, VEGA, TRITON

Current Milestone 100%

ANTILIA

Current Milestone 93%
Upcoming Milestone
Due
Tentative Date
On or before Possession
7%
Will be update soon

Structure Work: The main RCC (concrete) structure of the building is now fully completed up to the terrace level.

Masonry & Flooring: All internal blockwork and flooring have been completed up to the 30th floor.

Wall Finishing: Gypsum and cement plastering work is done on all floors, ensuring smooth, finished walls ready for painting and interiors.

Railings & Fixtures: MS railings are fully installed for added safety. Work on polishing the main doors and finishing window frames is actively underway on multiple floors.

Waterproofing & Kitchens: Waterproofing and kitchen platform installations have been completed up to the 30th floor, preparing homes for the next stage of interiors.

Fire Safety: The entire firefighting system has been fully installed across the building to ensure your safety and peace of mind.

Exterior Look: External painting is 85% complete, giving the tower its final appearance and adding to the overall aesthetic.

Elevators: Lift installation work is 75% complete, and soon all floors will have smooth and convenient access.

PHASE 2

CEDAR

Current Milestone 93%
Upcoming Milestone
Due
Tentative Date
On or before Possession
7%
will be updated soon

Structure Work: RCC (concrete) structure is fully completed up to the 28th floor, including the main superstructure.

Walls, Flooring & Plastering: Internal blockwork, flooring, and plastering are finished up to the 27th floor, giving shape to the interiors of your future home.

Plumbing & Kitchens: Internal plumbing lines and kitchen platform installations are also complete up to the 27th floor.

Safety First: The entire firefighting system has been fully installed across the building to ensure your safety.

Elevators: Lift installation is 75% complete—soon, all floors will be easily accessible.

Exterior Painting: External painting is 100% finished, giving the building its final and polished look.

Terrace Waterproofing: Waterproofing work on the terrace is complete, protecting the structure for the long run.

DAFFODIL

Current Milestone 93%
Upcoming Milestone
Due
Tentative Date
On or before Possession
7%
Will be updated soon

Structure Completed: RCC work, including the full superstructure, is now 100% complete.

Walls & Plumbing: Blockwork is fully done from the 1st to the 27th floor. Concealed internal plumbing has also been completed up to the 27th floor.

Staircase Finishing: Staircase flooring is finished till the 27th floor, ensuring smooth and safe movement within the tower.

Safety Systems: Firefighting and alarm systems are fully installed across the building, prioritizing safety for all residents.

Waterproofing: Waterproofing work is completed up to the 27th floor, adding long-term protection and durability to the structure.

BODHI

Current Milestone 85%
Upcoming Milestone
Due
Tentative Date
On Flat / Premises Completion
8%
15/03/25 – 15/05/25
On possession
7%
Will be updated soon

Structure Work: The superstructure RCC work, including the 28th floor slab and terrace slab, is now fully completed—along with the foundation and plinth slab.

Ground Floor Ready: All work on the ground floor is fully completed.

Flat Interiors: Flooring inside flats is completed up to the 27th floor, bringing the interiors closer to completion.

Walls & Plumbing: Blockwork is 100% done, and concealed plumbing is finished up to the 27th floor.

Wall Finishing: Gypsum plaster work has been completed till the 27th floor, giving walls a smooth and finished surface.

Doors: Door frame installation is done up to the 26th floor.

Fire Safety: Firefighting system installation is 100% complete, ensuring full building safety.

Lift Installation: Preparations for lift installation are underway to provide smooth access across all floors soon.

ASTER

Current Milestone 78%
Upcoming Milestone
Due
Tentative Date
On or after initiation of Lift-Stair lobby,etc (E)
7%
15/04/25 – 05/07/25
On or after initiation of Electrical / Painting of the flat / Premises
8%
05/05/25 – 27/07/25
On Flat / Premises Completion
3%
30/07/25
On possession
4%
Will be updated soon

Structural Work: The RCC structure is fully completed up to the 28th floor, including the terrace slab—marking a major milestone.

Strong Foundations: Foundation, columns, and plinth work are fully done, providing a strong and reliable base for the building.

Lower Ground Progress: Backfilling and ground slab work up to the Lower Ground level are completed.

Wall Work: Blockwork is finished up to the 27th floor, forming the internal layout of the homes.

Flooring & Kitchens: Flat flooring and kitchen platform installations are currently in progress across multiple floors.

Wall Finishing: Gypsum plastering has been completed up to the 22nd floor, giving a smooth finish to walls.

Plumbing: Concealed plumbing work is fully completed up to the 27th floor.

Fire Safety: Installation of the firefighting system is 60% complete and progressing steadily.

% mentioned above is the current demand due as per the construction linked payment schedule. The timeline for upcoming milestone mentioned above is tentative & only provide to enable better cash flow planning for customers. Actual timelines may vary as per site conditions.

AMENTIES

Swimming pool work 100% completed.

Kids play area 100% work completed.

Clubhouse work in progress. ( 75% completed & functional ) 