Construction Updates,
August 2024
Update as on 2nd August 2024
Zenith & Zodiac - Complete OC received
Avior, Acrux ,Ion , Vega - OC till 30th Floor
Atlas and Aura - OC till 29th floor
Altis - OC till 31st floor
Atria- OC till 26th floor
Phase 1
Phase 2
% mentioned above is the current demand due as per the construction linked payment schedule
OC received
OC received
Completed work up to Terrace slab level
OC received till 30th floor
Completed work up to Terrace slab level
OC received till 30th Floor.
Finishing work & RCC completed
OC received till 31st Floor.
Completed work up to Terrace slab level
OC received till 29th floor
Completed work up to Terrace slab level
OC received till 29th floor
Completed work up to Terrace slab level
OC received till 30th Floor.
RCC work completed
OC received till 26th floor
Superstructure RCC work completed up to terrace slab.
Block work 90% completed, flat flooring work in progress.
Gypsum & Cement plaster from 2nd to 30th floor completed.
MS railing work 97% done, and door/shutter polishing and window rough ground in progress across multiple floors
Waterproofing up to the 27th floor, kitchen platform work up to the 27th floor, and fire fighting installation 90% completed.
Substructure RCC work completed, flat flooring 100% done across all floors.
Toilet flooring from 1st to 30th floor and external painting up to terrace level completed.
Plumbing concealed work up to the 30th floor and door frame making across all floors finished.
Flat window frames and shutters are 95% installed, the remaining work is in progress
Tiling work is underway across multiple floors.
Fire fighting installation is 100% complete, lift handover/fixing preparation work is ongoing for L1, L2, L3, and L4 lifts to the 30th floor.
RCC work completed.
OC received till 30th Floor
Flat finishing work completed up to 31st floor.
Lift work & fire fighting installation work completed.
220 flat possession handover.
Superstructure RCC 28th slab completed
Ground to 28th floor RCC structure complete
Blockwork, flooring and plastering up to the 27th floor are finished.
Internal plumbing and kitchen platform completed till the 27th floor
Life installation is 75% complete, fire fighting system installed.
External painting and terrace water proofing nearly complete
RCC work completed
Superstructure RCC slab completed
Waterproofing done up to 27th floor
Balcony railing work finished from the 4th to the 27th floor (100% completion in ducts).
Block work 100% completed for floors 1st to 27th
Concealed plumbing finished up to the 27th floor.
Staircase flooring completed till 27th floor.
Superstructure RCC 28th floor slab completed
Superstructure RCC completed up to the 28th floor, including foundation and plinth slab.
Ground floor work is fully completed.
Flat flooring completed till 14th floor .
Block work completed
Concealed plumbing finished till the 22nd floor
Gypsum plaster work completed till the 18th floor.
Superstructure RCC 16th floor slab completed
Superstructure RCC slab completed up to 16th floor; 17th floor 75% completed.
Substructure RCC foundation and column till LG fully completed.
Backfilling and grad slab done till LG level
Plinth checking completed; ground floor slab casted
Window work in progress
Amenities work in progress
Swimming pool work 100% completed.
Kids play area 100% work completed.
Clubhouse work in progress. ( 60% completed & functional )
TOWER | FLOOR DETAILS | DETAILED UPDATES |
---|---|---|
Zenith | Completed | OC received |
Zodiac | Completed | OC received |
Acrux | Completed work up to Terrace slab level | Part OC received till 24th floor
RCC work complete till terrace slab Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor Door & shutter polish completed till the 31st floor & single coat polish done on above floors. Cp & sanitary Flat completed till the 31st floor Stair case – flooring & skirting completed till B2 To 31st floors Stair case – window work completed till the terrace Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor Entrance lobby work completed Society office work completed External Painting work completed till the 24 th floors & 25th to 31st 95% completed. Terrace water proofing completed & flooring work done 70% Concealed plumbing work completed from 1st to 31st floor Fire fighting Delivery material & installation work completed B2 to 31st floor Fire alarm work completed B2 to 31st floor. testing & commissioning completed Lift completed from B2 to 31st floor ( 4 nos ) |
Ion | Completed work up to Terrace slab level | RCC completed till terrace floor
Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 1st to 31st floor completed , door frames main door 1st to 31st and block work toilet 1st to 31st floor 100% completed External painting putty , primer, texture base completed from basement 1st to terrace in flat 01,02,05,06,07,08 100 % .Flat 3 & 4 work in progress Plumbing Duct & Open duct Painting-100% completed Lift 100% completed basement to 31st floor Fire fighting installation 100% completed |
Avior | Completed work up to Terrace slab level | Part OC received till 24th Floor
RCC work complete till terrace slab Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor Stair case work completed from b2 to 31st floor Entrance lobby work completed Lift lobby completed till the 31st floor & painting work completed till 31st floor Refuge floor completed Stilt floor work completed Electrification service completed till 31st floor Plumbing service completed in flat & servant toilet work completed till the 31st floor. Fire fighting completed B2 to 31st floors & handover to facility Lift all completed from B2 to 31st |
Vega | Completed work up to Terrace slab level | RCC completed till terrace floor,
1st floor to 31st floor Conceal plumbing work completed Waterproofing 1st to 31st Floor completed 1st to 31st floor 100% completed (Ledge wall) External painting texture work 90% completed Lift 70% completed Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed Terrace water proofing 100% completed |
Antilia | Excavation completed | Foundation work 100% completed , plinth slab 100% completed. Stilt slab 100% completed , 1st Slab 100% completed |
Aura | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC work completed till terrace level Possession flat 103 done Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing Painting work 1st to 30th 100% completed External painting 1st to 30th floor 100% completed stilt painting 85% completed Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor |
Atlas | Completed work up to Terrace slab level | Part OC received till 20th floor
RCC completed till terrace floor Flat finishing completed 100% Possession flat – 120 done External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100% Terrace water proofing completed & flooring work done 90% Concealed plumbing completed 100% Fire fighting installation B1 & b2 building from 1st to 30th floor completed Lift 100% completed Entrance lobby , society office , stair case , lift lobby completed 100% |
Triton | Substructure RCC work completed | UGWT RCC completed
Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed |
Altis | Finishing work & RCC completed | RCC completed till terrace floor
Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed Door frame fixing work completed till 32nd floor 100% completed Lift L1,L2.L3,L4 100% completed basement to 32nd floor Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed |
Cedar | Excavation completed | Substructure RCC work ground floor slab 103.75mm completed
UGWT completed Superstructure RCC work upto 4th floor completed.5th floor 50% completed. |
Atria | RCC work completed | Substructure RCC work completed
Flat finishing work 5% completed , UGWT , Superstructure RCC work , OHWT & LMR work completed |