Construction Updates,
May 2026

Update as on 4th May 2026

PHASE 1 – 12 Towers Delivered

ZENITH, ZODIAC, ACRUX, ALTIS, ATLAS, ATRIA, AURA, AVIOR, ION, VEGA, TRITON, ANTILIA

Completion 100%

PHASE 2

CEDAR , DAFFODIL 

OC RECEIVED

Completion 100%

BODHI

Milestone
Due
Tentative Date
Due
93%
NA
On Possession
7%
Will be updated soon

The entire RCC structure, including the 28th floor slab and terrace slab, is fully completed — along with the foundation and plinth.

Ground floor work is fully finished.

Inside the homes, flooring is completed till the 27th floor, making the interiors feel almost move-in ready.

Wall work is 100% done, with smooth gypsum plaster finishing completed till the 27th floor.

Concealed plumbing lines are also finished up to the 27th floor.

Door frames are already in place till the 27th floor, and door hardware installation (locks, handles, etc.) is now in progress.

Windows are 80% installed, with balance work ongoing.

Tiling work inside homes is completed, adding the final touches to the interiors.

Firefighting system installation is 100% done, and the Chief Fire Officer’s inspection is scheduled soon.

Lift installation is in progress, ensuring smooth connectivity across all floors.

ASTER

Milestone
Due
Tentative Date
Due
93%
NA
On Flat / Premises Completion / on possession
3%
Will update soon

The entire RCC structure is complete up to the 28th floor, including the terrace slab. Foundation, columns, and plinth work are also fully done.

Blockwork (internal walls) is complete till the 28th floor, shaping the homes across the tower.

Gypsum plastering is completed till the 28th floor.

Flooring and kitchen platforms are in progress — tiling work is finished up to the 28th floor and Kitchen platform work till 28th floor completed

Waterproofing is done till the 28th floor

Plumbing (CPVC concealed lines) is fully completed, ensuring proper water supply and drainage.

Firefighting systems are installed till the 28th floor.

Lift installation is almost done, with the final brackets now being installed.

Staircase tiling is completed, and painting work across the tower is 95% completed

UPCOMING PHASE 3 ( NIRVANA )

 

PHASE 3 – NIRVANA

NIRVANA TOWER A 

Milestone
Due
Tentative Date
On booking
10%
2032

Excavation Work 99% completed

Footing & column reinforcement binding work completed 85% , Footing casting completed 75%, Column casting till tie beam completed 95% , Plinth beam pic 10% , Plinth beam reinforcement work 5 % completed 

NIRVANA TOWER B 

Milestone
Due
Tentative Date
On booking
10%
2032

Excavation Work 95% completed

Footing & column reinforcement binding work completed 50% , Footing casting completed 13%, Column casting work till 5

NIRVANA TOWER C

Milestone
Due
Tentative Date
On booking
10%
2032

Excavation Work 30% completed

AMENITIES

Swimming Pool,  Kids Play Area, Sports Court – Operational

Clubhouse work in progress –  80% completed & functional

% mentioned above is the current demand due as per the construction linked payment schedule. The timeline for upcoming milestone mentioned above is tentative & only provide to enable better cash flow planning for customers. Actual timelines may vary as per site conditions.

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.