CONSTRUCTION UPDATES, JANUARY 2022

Update as on 3rd January, 2022

CONSTRUCTION UPDATES, JANUARY 2022

Update as on 3rd January, 2022

Completion
46%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor DetailsDetailed Updates
Substructure RCC Work100 % Completed
Superstructure RCC Work100 % RCC 7th Slab completed, 8th slab 50 % completed.
Shop Finishing -Block workGround floor shop blockwork 70% completed