CONSTRUCTION UPDATES, July 2022

Update as on 6th July, 2022

CONSTRUCTION UPDATES, July 2022

Update as on 6th July, 2022

Completion
62%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor Details Detailed Updates
Substructure RCC Work 100 % Completed
Superstructure RCC Work 100 % RCC 14th Slab completed & 15th slab in progress.
Shop Finishing -Block work Ground floor shop block work 70% completed