CONSTRUCTION UPDATES, October 2022
Update as on 6th October, 2022
CONSTRUCTION UPDATES, October 2022
Update as on 6th October, 2022
Completion
% mentioned above is the current demand due as per the construction linked payment schedule
Floor Details | Detailed Updates |
---|---|
Substructure RCC Work | 100 % Completed |
Superstructure RCC Work | 100 % RCC 17th Slab completed & 18th RCC slab in progress. ( 10% completed) |
Shop Finishing -Block work | Ground floor shop block work 80% completed |
Common Area finishing work | Entrance lobby marble flooring 70% completed, Fire fighting double height Sprinkler & FAPA installation completed – 90% |
MARATHON REFERRAL AND LOYALTY PROGRAM
MARATHON REFERRAL AND LOYALTY PROGRAM
![marathon_digital_referral-illustration_01](https://marathon.in/millennium/wp-content/uploads/sites/34/2022/04/marathon_digital_referral-illustration_01.png)
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.