CONSTRUCTION UPDATES, JANUARY 2022

Update as on 3rd January, 2022

CONSTRUCTION UPDATES, JANUARY 2022

Update as on 3rd January, 2022

Completion
46%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor Details Detailed Updates
Substructure RCC Work 100 % Completed
Superstructure RCC Work 100 % RCC 7th Slab completed, 8th slab 50 % completed.
Shop Finishing -Block work Ground floor shop blockwork 70% completed