CONSTRUCTION UPDATES, January 2023

Update as on 4th January, 2023

CONSTRUCTION UPDATES,Jauary 2023

Update as on 4th January, 2023

Completion
70%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor Details Detailed Updates
Substructure RCC Work 100 % Completed
Superstructure RCC Work 100 % RCC 20th Slab completed & 21st RCC slab in progress. ( 70% completed)
Shop Finishing -Block work Ground floor shop block work 80% completed
Common Area finishing work Entrance lobby marble flooring 100% completed, Fire fighting double height Sprinkler & FAPA installation completed – 90% , Fire fighting 1st, 4th, 5th, 6th ,10th ,11th floor area completed.