CONSTRUCTION UPDATES, July 2022

Update as on 6th July, 2022

CONSTRUCTION UPDATES, July 2022

Update as on 6th July, 2022

Completion
62%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor DetailsDetailed Updates
Substructure RCC Work100 % Completed
Superstructure RCC Work100 % RCC 14th Slab completed & 15th slab in progress.
Shop Finishing -Block workGround floor shop block work 70% completed

MARATHON REFERRAL AND LOYALTY PROGRAM

MARATHON REFERRAL AND LOYALTY PROGRAM

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.