Completion
38%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor DetailsDetailed Updates
Substructure RCC Work100 % Completed
Superstructure RCC Work100 % RCC 4th Slab completed, 5th slab 70 % completed.