CONSTRUCTION UPDATES, OCTOBER 2023

Update as on 3rd October, 2023

CONSTRUCTION UPDATES, OCTOBER 2023

Update as on 3rd October, 2023

OC RECEIVED TILL 20TH FLOOR

Completion
85%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor DetailsDetailed Updates
Substructure RCC Work100 % Completed
Superstructure RCC Work25th RCC Slab completed & 26th  RCC slab in progress. ( 50% completed)
Shop Finishing -Block workGround floor shop block work 80% completed
Common area finishing workEntrance lobby completed .
Electrical panel installation completed .
Fire fighting services completed from floor 1st to 20th.
City lift installation 100% completed.
Stair case work in progress

MARATHON REFERRAL AND LOYALTY PROGRAM

MARATHON REFERRAL AND LOYALTY PROGRAM

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.