CONSTRUCTION UPDATES, September 2023

Update as on 4th September, 2023

CONSTRUCTION UPDATES,September 2023

Update as on 4th September, 2023

Completion
80%

% mentioned above is the current demand due as per the construction linked payment schedule

Floor DetailsDetailed Updates
Substructure RCC Work100 % Completed
Superstructure RCC Work25th RCC Slab completed & 26th  RCC slab in progress. ( 50% completed)
Shop Finishing -Block workGround floor shop block work 80% completed
Common area finishing workEntrance lobby completed .
Electrical panel installation completed .
Fire fighting services completed from floor 1st to 20th.
City lift installation 100% completed.