Construction Updates,December 2024

Check updates:
NeoSkiesNeoHills
NeoSquareNeoValley • NeoPark

Update as on 10th December, 2024

NeoSkies
100%
NeoHills
100%
NeoSquare
95%
NeoValley Kaveri A
20%
NeoValley Kaveri B
42%
NeoValley Narmada
20%
NeoPark - A
67%
NeoPark - B
50%

% mentioned above is the current demand due as per the construction linked payment schedule

NeoSkies – Sale building
OC Received
NeoSkies – Sale building

RCC work
Top RCC slab 100% completed.

Finishing work
Waterproofing work in progress ( 100% completed)
Conceal plumbing work in progress ( 100% completed)
Gypsum work 100% completed .
Flat flooring work 100% completed.
Door shutter work 99% completed.
Flat window work 99% completed.

NeoSkies – Rehab building

RCC work
OC received

Finishing work
177 flat possession handover

Infra
Sewage Treatment Plant &  Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.

NeoHills – Sale building
OC Received
NeoSquare – A wing

RCC work
RCC 100% work completed

Flat Finishing
Block work finalized till terrace floor
Electric concealed work completed & Electrical wiring work completed 100%
Gypsum plaster work 95% completed
Waterproofing & plumbing work completed till top floor
Flat tiling work & door frames work completed at 2nd to 22nd floor & 1st floor in progress
Lift lobby tiling work completed at 2nd  to 22nd floor
Main door frames making & fixing work completed till 22nd floor
External painting work completed

RCC Infra
UG water tank civil work completed &  domestic & fire tank work in progress.

NeoSquare – B wing

RCC work completed till top slab.

Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed .
Staircase flooring is completed from ground floor to till terrace.
Electric duct FRD door are fixed.
Schindler lift installation completed.
External painting work completed & Internal painting work in progress.( 90% completed)

NeoSquare – C wing

RCC work
RCC  completed till top slab

Flat finishing
Kitchen extension work completed till top floor
Concealed plumbing & waterproofing is completed.
Electrical conducting work completed
Terrace waterproofing work completed .

Common area finishing
Completed

NeoValley  ( Kaveri ) – Sale building  B 

Excavation work 100% completed .
PCC work 100% completed.
Footing work 100% completed.
Foundation & plinth work completed.
9th slab work completed

NeoValley  ( Kaveri ) – Sale building A

Excavation & footing work 100% completed .
Part plinth work completed

NeoValley ( Kaveri ) – Rehab building ( Sahjeevan )

RCC work
RCC work completed till top slab

Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover

NeoValley  ( Narmada ) – Sale building C

construction not commenced yet

NeoValley  ( Narmada ) – Sale building B

Excavation for non tower area work 75 % completed
Foundation & Excavation work in progress.

NeoValley  ( Narmada ) – Rehab building A

Foundation work 100% completed.
plinth work 100 % completed)

NeoPark – Rehab Building D wing

RCC work
Plinth RCC work 100% completed.
21st slab work completed
Block work completed till 19th floor & Gypsum work completed till 15th floor .

NeoPark – Sales building A wing

RCC work
Piling work completed .
Substructure work in progress
Plinth work completed & 1st to 22nd slab work completed.
Block work completed till 13th floor & gypsum work completed till 6th floor

NeoPark – Sales building B wing

RCC work
Foundation work completed  & substructure work in progress.
Plinth work completed.
RCC 11th slab work completed

NeoPark – Sales building C wing

RCC work
Excavation work 100% completed & Foundation work Completed
Substructure work completed 70 %

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work completed till 20th slab & 21st floor slab 5% completed
Finishing work Blockwork completed till 15th floor
Plumbing Conceal work completed upto 15th floor
Gypsum work completed upto 14th floor
Water proofing completed upto 11th floor
Flat flooring completed upto 4th floor
Infra STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed.
NeoSkies – Sale building RCC work Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% .
NeoHills – Rehab building RCC work Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress.
NeoHills – Sale building RCC work Substructure work 100% completed
Superstructure 1st floor slab in progress.
NeoSquare – A wing RCC work 2nd Slab completed
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor)
Common area finishing Gypsum on some of the floors completed
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 10th floor level
Chajja casting completed.
Flat finishing Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed
Common area finishing Completed
Services Services of extra flat(PAP unit flat No 7) is pending rest is completed

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.