Construction Updates, April 2024

Check updates:
NeoSkiesNeoHills
NeoSquareNeoValley • NeoPark

Update as on 3rd April, 2024

NeoSkies
95%
NeoHills
90%
NeoSquare
73%
NeoValley
20%
NeoPark
40%

% mentioned above is the current demand due as per the construction linked payment schedule

NeoSkies – Sale building

RCC work
Top RCC slab 100% completed.

Finishing work
Waterproofing work in progress ( 100% completed)
Conceal plumbing work in progress ( 100% completed)
Gypsum work 99% completed .
Flat flooring work 99% completed.
Door shutter work 99% completed.
Flat window work 94% completed.

NeoSkies – Rehab building

RCC work
OC received

Finishing work
177 flat possession handover

Infra
Sewage Treatment Plant &  Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.

NeoHills – Sale building

RCC work
23rd RCC slab completed

Finishing work
Waterproofing work in progress ( 93% completed)
Conceal plumbing work in progress ( 92% completed)
Gypsum work 80% completed .
Flat flooring work 94% completed.
Flat door shutter work 92% completed.
Flat window work 65% completed.

NeoHills – Rehab building

RCC work
Pile, Excavation ,Substructure &  Superstructure work 100% completed

NeoSquare – A wing

RCC work
23rd slab casting completed & LMR casting completed.

Flat Finishing
Block work finalized till 21st floor & 22nd floor work in progress.
Electric concealed work completed till 21st floor.
Gypsum plaster work completed till skirting level at 3rd, 5th to 20th floor & 21st floor work in progress.
Waterproofing & plumbing work completed at 3rd, 5th to 20th floor & 21st floor work in progress.
Flat tiling work & door frames work completed at 3rd ,5th to 19th floor .
Lift lobby tiling work completed at 3rd & 5th to 19th floor , 20th floor work in progress.
Main door frames making & fixing work completed till 18th floor , 19th floor work in progress.
External painting work in progress.

RCC Infra
UG water tank civil work completed &  domestic & fire tank work in progress.

NeoSquare – B wing

RCC work completed till top slab.

Flat Finishing
Concealed plumbing completed
Hall extension civil work , Flooring , Gypsum plaster work completed .
Staircase flooring is completed from ground floor to till terrace.
Electric duct FRD door are fixed.
Schindler lift installation completed.
External painting work completed & Internal painting work in progress. (60% completed)

NeoSquare – C wing

RCC work
RCC  completed till top slab

Flat finishing
Kitchen extension work completed from 4th to 19th floor & 3rd floor work in progress.
Concealed plumbing completed from 4th to 19th floor, waterproofing is completed from 4th to 19th floor.
Electrical conducting work completed till 19th floor.
Terrace waterproofing work completed .

Common area finishing
Completed

NeoValley  ( Kaveri ) – Sale building 

Excavation work 100% completed .
PCC work 100% completed.
Footing work 100% completed.
Column & Retaining wall work 60% completed.

NeoValley ( Kaveri ) – Rehab building ( Sahjeevan )

RCC work
RCC work completed till top slab

Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover

NeoValley  ( Narmada ) – Sale building 

construction not commenced yet

NeoValley  ( Narmada ) – Rehab building 

Foundation work 60% completed.

NeoPark – Rehab Building D wing

RCC work
Plinth RCC work 100% completed.
10th slab work completed.

NeoPark – Sales building A wing

RCC work
Piling work completed .
Substructure work in progress
Plinth work completed & 1st to 4th slab work completed.

NeoPark – Sales building B wing

RCC work
Foundation work completed  & substructure work in progress.
Plinth shuttering work in progress.

NeoPark – Sales building C wing

RCC work
Excavation work 100% completed & Foundation work started

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work completed till 20th slab & 21st floor slab 5% completed
Finishing work Blockwork completed till 15th floor
Plumbing Conceal work completed upto 15th floor
Gypsum work completed upto 14th floor
Water proofing completed upto 11th floor
Flat flooring completed upto 4th floor
Infra STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed.
NeoSkies – Sale building RCC work Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% .
NeoHills – Rehab building RCC work Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress.
NeoHills – Sale building RCC work Substructure work 100% completed
Superstructure 1st floor slab in progress.
NeoSquare – A wing RCC work 2nd Slab completed
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor)
Common area finishing Gypsum on some of the floors completed
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 10th floor level
Chajja casting completed.
Flat finishing Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed
Common area finishing Completed
Services Services of extra flat(PAP unit flat No 7) is pending rest is completed

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.