% mentioned above is the current demand due as per the construction linked payment schedule
NeoSkies – Sale building
OC Received
NeoSkies – Sale building
RCC work
Top RCC slab 100% completed.
Finishing work
Waterproofing work in progress ( 100% completed)
Conceal plumbing work in progress ( 100% completed)
Gypsum work 100% completed .
Flat flooring work 100% completed.
Door shutter work 99% completed.
Flat window work 99% completed.
NeoSkies – Rehab building
RCC work
OC received
Finishing work
177 flat possession handover
Infra
Sewage Treatment Plant & Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.
NeoHills – Sale building
OC Received
Neo Square – Sale building
OC Received
NeoValley ( Kaveri ) – Sale building B
Excavation, Foundation & Base Work – Excavation, PCC, Footing work 100% completed .
Structural Progress – RCC slab for the 22nd floor has been completed. terrace slab work completed. Finishing work completed till 18th floor & External Painting work in progress
NeoValley ( Kaveri ) – Sale building A
Foundation Work – Excavation and footing work are 100% completed.
Plinth work is also fully done, forming a solid base for the structure.
Structural Progress – RCC slab work from the 1st to 15th floors is completed & 16th floor slab work is currently in progress
NeoValley ( Kaveri ) – Rehab building ( Sahjeevan )
RCC work
RCC work completed till top slab
Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover
NeoValley ( Narmada ) – Sale building C
construction not commenced yet
NeoValley ( Narmada ) – Sale building B
Excavation Work– Foundation & Excavation work 100% completed & plinth 100 % completed
NeoValley ( Narmada ) – Rehab building A
Foundation & Base Work -Foundation and plinth work are now 100% completed, providing a strong and stable base for the building.
Structural Progress – RCC slab work from the 1st to the 16th floor is fully completed.
NeoPark – Rehab Building D wing
Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 22nd floor is fully completed & terrace slab casting 100% completed
Finishing– Blockwork is completed up to the 19th floor , Gypsum plastering, electrical work is completed . common area work completed till 18th floor . Fire fighting work 100 % completed
NeoPark – Sales building A wing
Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 22nd floor is fully completed.
Finishing– Blockwork is completed up to the 22nd floor , Gypsum plastering is completed up to the 22nd floor , Flat Tiling work completed from 2nd to 22nd floor , Window work completed 22nd floor, lift installation work in progress. Fire fighting work 100 % completed
NeoPark – Sales building B wing
Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 22nd floor is fully completed , Block work completed till 22nd floor & gypsum plastering completed till 22nd floor. Tiling work completed from 3rd to 22nd floor, Lift installation completed & common area tiling work completed 100 % , Fire Fighting work completed 100 % .
NeoPark – Sales building C wing
Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work completed till 11th floor & 12th slab in progress
| Tower | Floor Details | Detailed Updates |
|---|---|---|
| NeoSkies – Rehab building | RCC work | RCC work completed till 20th slab & 21st floor slab 5% completed |
| Finishing work | Blockwork completed till 15th floor Plumbing Conceal work completed upto 15th floor Gypsum work completed upto 14th floor Water proofing completed upto 11th floor Flat flooring completed upto 4th floor |
|
| Infra | STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed. | |
| NeoSkies – Sale building | RCC work | Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% . |
| NeoHills – Rehab building | RCC work | Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress. |
| NeoHills – Sale building | RCC work | Substructure work 100% completed Superstructure 1st floor slab in progress. |
| NeoSquare – A wing | RCC work | 2nd Slab completed |
| NeoSquare – B wing | Ground to OHWT | RCC completed |
| Flat Finishing | Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor) | |
| Common area finishing | Gypsum on some of the floors completed | |
| Services | Only fire fighting completed | |
| NeoSquare – C wing | RCC | RCC of main building completed PAP unit – extension flat at 10th floor level Chajja casting completed. |
| Flat finishing | Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed | |
| Common area finishing | Completed | |
| Services | Services of extra flat(PAP unit flat No 7) is pending rest is completed |
Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.










