Construction Updates,February 2026

Check updates:
NeoSkiesNeoHills
NeoSquareNeoValley • NeoPark

Update as on 8th February, 2026

NeoSkies
100%
NeoHills
100%
NeoSquare
100%
NeoValley Kaveri A
64%
NeoValley Kaveri B
72%
NeoValley Narmada
40%
NeoPark - A
95%
NeoPark - B
95%

% mentioned above is the current demand due as per the construction linked payment schedule

NeoSkies – Sale building
OC Received
NeoSkies – Sale building

RCC work
Top RCC slab 100% completed.

Finishing work
Waterproofing work in progress ( 100% completed)
Conceal plumbing work in progress ( 100% completed)
Gypsum work 100% completed .
Flat flooring work 100% completed.
Door shutter work 99% completed.
Flat window work 99% completed.

NeoSkies – Rehab building

RCC work
OC received

Finishing work
177 flat possession handover

Infra
Sewage Treatment Plant &  Plain Cement Concrete- 100% completed, Raft 100% completed , wall casting 100% completed , Top slab casting 100% completed.

NeoHills – Sale building
OC Received
Neo Square – Sale building
OC Received
NeoValley  ( Kaveri ) – Sale building  B 

Excavation, Foundation & Base Work – Excavation, PCC, Footing work 100% completed .
Structural Progress – RCC slab for the 22nd floor has been completed. terrace slab work completed. Finishing work completed till 18th floor & External Painting work in progress

NeoValley  ( Kaveri ) – Sale building A

Foundation Work – Excavation and footing work are 100% completed.
Plinth work is also fully done, forming a solid base for the structure.
Structural Progress – RCC slab work from the 1st to 15th floors is completed & 16th floor slab work is currently in progress

NeoValley ( Kaveri ) – Rehab building ( Sahjeevan )

RCC work
RCC work completed till top slab

Flat finishing
Internal & external finishing work completed 100%
165 flat possession handover

NeoValley  ( Narmada ) – Sale building C

construction not commenced yet

NeoValley  ( Narmada ) – Sale building B

Excavation Work– Foundation & Excavation work 100% completed & plinth 100 % completed

NeoValley  ( Narmada ) – Rehab building A

Foundation & Base Work -Foundation and plinth work are now 100% completed, providing a strong and stable base for the building.
Structural Progress – RCC slab work from the 1st to the 16th floor is fully completed.

NeoPark – Rehab Building D wing


Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 22nd floor is fully completed & terrace slab casting  100% completed
Finishing– Blockwork is completed up to the 19th floor , Gypsum plastering, electrical work is completed . common area work completed till 18th floor . Fire fighting work 100 % completed

NeoPark – Sales building A wing


Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 22nd floor is fully completed.
Finishing– Blockwork is completed up to the 22nd floor , Gypsum plastering is completed up to the 22nd floor , Flat Tiling work completed from 2nd to 22nd floor , Window work completed 22nd floor, lift installation work in progress. Fire fighting work 100 % completed

NeoPark – Sales building B wing


Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work from the 1st to the 22nd floor is fully completed , Block work completed till 22nd floor & gypsum plastering completed till 22nd floor. Tiling work completed from 3rd to 22nd floor, Lift installation completed & common area tiling work completed 100 % , Fire Fighting work completed 100 % .

NeoPark – Sales building C wing


Foundation & Substructure – Plinth work is 100% completed
Structural Progress– RCC slab work completed till 11th floor & 12th slab in progress

Tower Floor Details Detailed Updates
NeoSkies – Rehab building RCC work RCC work completed till 20th slab & 21st floor slab 5% completed
Finishing work Blockwork completed till 15th floor
Plumbing Conceal work completed upto 15th floor
Gypsum work completed upto 14th floor
Water proofing completed upto 11th floor
Flat flooring completed upto 4th floor
Infra STP pcc- 100% done, Raft r/f 100% completed , wall casting 60% completed , Top slab casting 20% completed.
NeoSkies – Sale building RCC work Plinth – 100% completed, 1st & 2nd Slab 100% completed, 3rd Slab completed till 30% .
NeoHills – Rehab building RCC work Pile , Excavation & Substructure work 100% completed , Superstructure 15th slab work in progress.
NeoHills – Sale building RCC work Substructure work 100% completed
Superstructure 1st floor slab in progress.
NeoSquare – A wing RCC work 2nd Slab completed
NeoSquare – B wing Ground to OHWT RCC completed
Flat Finishing Concealed plumbing completed Kitchen platform, flooring, gypsum, door installation completed (till 16th floor)
Common area finishing Gypsum on some of the floors completed
Services Only fire fighting completed
NeoSquare – C wing RCC RCC of main building completed
PAP unit – extension flat at 10th floor level
Chajja casting completed.
Flat finishing Kitchen extension work at 9th floor is in progress Rest finishing inside the flat is completed
Common area finishing Completed
Services Services of extra flat(PAP unit flat No 7) is pending rest is completed

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.