Construction Updates, April 2020.
Construction Updates, April 2020.
Emerald Tower external painting completed
The construction at Marathon Nextown is proceeding speedily. More than 80 families are already staying in the 3 completed towers. Emerald tower’s external painting completed, Coral till 16th slab and the 1st floor is completed for Sapphire. Please refer to the table below for detailed updates
Emerald
Detailed updates (Possession – June 2020):
Water Proofing & Gypsum Plaster completed
RCC work 100% completed- OHWT and LMR is constructed
Internal Civil work completed till 19th floor
Flooring (except 13, 15, 17 floor) completed
External painting is completed
Coral
Detailed updates (Possession – June 2020):
RCC work 16th slab completed
Waterproofing 3rd floor onwards
Gypsum plaster 7th floor in progress
Electrification 15th slab completed
Plumbing work 9th floor in progress – 75% completed
Sapphire
Detailed updates (Possession – June 2021):
RCC work – 1st slab completed
Emerald
Detailed updates (Possession – June 2020):
Water Proofing & Gypsum Plaster completed
RCC work 100% completed- OHWT and LMR is constructed
Internal Civil work completed till 19th floor
Flooring (except 13, 15, 17 floor) completed
External painting is completed
Coral
Detailed updates (Possession – June 2020):
RCC work 16th slab completed
Waterproofing 3rd floor onwards
Gypsum plaster 7th floor in progress
Electrification 15th slab completed
Plumbing work 9th floor in progress – 75% completed
Sapphire
Detailed updates (Possession – June 2021):
RCC work – 1st slab completed