Construction Updates,March 2023
Update as on 2nd March, 2023
Construction Updates,March 2023
Update as on 2nd March, 2023
% mentioned above is the current demand due as per the construction linked payment schedule.
Tower Name | Detailed Updates |
---|---|
Opal |
OC Received |
Topaz |
OC Received |
Amber |
OC Received |
Emerald |
OC Received |
Coral |
OC Received |
Sapphire |
14th slab RCC completed. |
Ruby |
Excavation 100% completed. |
Amenities | Updates |
---|---|
Club House |
Plinth beam work 100% completed,Back filling 100% completed & Stilt level PCC 100% completed. Superstructure 1st floor column 75% completed. |
![marathon-nextown-dombivli-layout-copy](https://marathon.in/nextown/wp-content/uploads/sites/6/2021/03/marathon-nextown-dombivli-layout-copy.jpg)
Emerald
Possession Date: Dec 2022
OC Received
Sapphire
Possession Date: Jun 2023
RERA No.: P51700001265
Coral
Possession Date: Jun 2023
RERA No.: P51700000952
Ruby
Possession Date: Dec 2026
RERA No.: P51700021189
Marathon Referral and Loyalty Program
Marathon Referral and Loyalty Program
![marathon_digital_referral-illustration_01](https://marathon.in/nextown/wp-content/uploads/sites/6/2022/04/marathon_digital_referral-illustration_01.png)
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.