Construction Updates,July 2026

Update as on 6th July 2026

Construction Updates,July 2026

Update as on 6th July, 2026

Ruby
80%
Jasper
55%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

OC Received 

Sapphire

OC Received 

Ruby

Structural Work: The RCC (Reinforced Concrete) structure is fully completed up to the 22nd floor, including the terrace slab.
Foundation & Base Work: The foundation, stub columns, plinth beams, and backfilling are 100% complete, ensuring a strong base for the building.
Block Work: Brick/blockwork is completed up to the 22nd floor
Plastering Work: Internal gypsum plastering is finished up to the 22nd floor, with higher floors in progress. Lift lobby plastering is currently underway

Jasper

Excavation Work: Completed.
Foundation & Basement: 100% of the base structure is ready.
RCC Wall Construction: 8th floor slab completed & 9th slab work in progress
Amenities  Updates

Club House

Terrace slab work completed

Foundation & Slabs: All sub-structure work, including the foundation, 1st floor slab, and terrace/roof slab, is completed.

Amenities : Multipurpose hall structure completed, Indoor games room and fitness center development in progress,

Finishing Work: Flooring work initiated in indoor activity zones, Electrical conduit and wiring works completed in common areas,Plumbing and drainage installations in progress, Fire-fighting system piping installation underway, Ceiling framework and painting preparation in progress,&  Door and window frame installation completed in key areas.

Blockwork: Internal and external blockwork completed up to terrace level, Partition wall work completed in designated areas

Plastering: Internal plastering work completed  & external plastering work in progress

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2024
OC Received

Coral

Possession Date: Jun 2023
OC Received

Ruby

Possession Date: Dec 2026
RERA No.: P51700021189

Jasper

Possession Date: Dec 2028
RERA No.: P51700049449

Marathon Referral and Loyalty Program

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.