Construction Updates, Oct 2020.

EMERALD
CORAL
SAPPHIRE
Tower Name Floor details Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

Completed work up to Terrace slab level

Detailed updates (Possession – Dec 2020)
Water Proofing & Gypsum Plaster completed
RCC work 100% completed- OHWT and LMR is constructed
Internal Civil work completed till 19th floor
Flooring (except 13, 15, 17 floor) completed
External painting is completed
All lifts completed

Coral

Completed 16th slab level

Detailed updates (Possession – Dec 2020)
RCC 16th slab completed, only terrace slab balance
Waterproofing 3rd floor onwards
Gypsum plaster 7th floor in progress
Electrification 15th slab completed
Plumbing work 9th floor in progress – 75% completed

Sapphire

Completed  1st slab level

Detailed updates (Possession – Dec 2021)
RCC work – 1st slab completed

Emerald

Possession Date: Dec 2020
RERA No.: P51700000686

Coral

Possession Date: Dec 2020
RERA No.: P51700000952

Sapphire

Possession Date: Dec 2021
RERA No.: P51700001265