Construction Updates, Nov 2019.

Emerald Tower external painting completed

The construction at Marathon Nextown is proceeding speedily. More than 80 families are already staying in the 3 completed towers. Emerald tower’s external painting completed, Coral till 14th slab and the 1st floor is in progress for Sapphire. Please refer to the table below for detailed updates

Emerald

Detailed updates (Possession – June 2020):
RCC work 100% completed- OHWT and LMR is constructed
Finishing work done till 18th Floor-80% work is completed
Internal Civil work completed till 19th floor
Waterproofing, plumbing and tiling in progress from 18th floor onwards
External painting is completed. Terrace tiling completed

Coral

Detailed updates (Possession – June 2020):
RCC work 60% completed- 14th slab completed
Internal Civil work completed til 9th floor
Waterproofing, plumbing and tiling in progress from 2nd floor onwards

Sapphire

Detailed updates (Possession – June 2021):
RCC work 10% completed- 1st floor is in progress

Emerald

Detailed updates (Possession – June 2020):
RCC work 100% completed- OHWT and LMR is constructed
Finishing work done till 18th Floor-80% work is completed
Internal Civil work completed till 19th floor
Waterproofing, plumbing and tiling in progress from 18th floor onwards
External painting is completed. Terrace tiling completed

Coral

Detailed updates (Possession – June 2020):
RCC work 60% completed- 14th slab completed
Internal Civil work completed til 9th floor
Waterproofing, plumbing and tiling in progress from 2nd floor onwards

Sapphire

Detailed updates (Possession – June 2021):
RCC work 10% completed- 1st floor is in progress