Construction Updates,June 2025
Update as on 5th June 2025
Construction Updates,June 2025
Update as on 5th June, 2025
% mentioned above is the current demand due as per the construction linked payment schedule.
Tower Name | Detailed Updates |
---|---|
Opal |
OC Received |
Topaz |
OC Received |
Amber |
OC Received |
Emerald |
OC Received |
Coral |
OC Received |
Sapphire |
OC Received |
Ruby |
Structural Work: The RCC (Reinforced Concrete) structure is fully completed up to the 22nd floor, including the terrace slab. |
Jasper |
Excavation Work: Completed. Foundation & Basement: 100% of the base structure is ready. RCC Wall Construction: 1st floor slab completed & 2nd slab mivan setting work in progress |
Amenities | Updates |
---|---|
Club House |
Terrace slab work completed Foundation & Slabs: All sub-structure work, including the foundation, 1st floor slab, and terrace/roof slab, is completed. LMR Progress: LMR (Lift Machine Room) column reinforcement work has been successfully completed. Multipurpose Court: The outdoor multipurpose court is 100% complete and ready. Internal Work: Internal electrical work is fully completed, ensuring power systems are in place. Blockwork: Blockwork is completed all the way up to the terrace level. Ground and 1st-floor blockwork is also done. Plastering: External cement plastering is 100% completed, giving the tower its refined outer appearance. |

Emerald
Possession Date: Dec 2022
OC Received
Sapphire
Possession Date: Jun 2024
OC Received
Coral
Possession Date: Jun 2023
OC Received
Ruby
Possession Date: Dec 2026
RERA No.: P51700021189
Jasper
Possession Date: Dec 2028
RERA No.: P51700049449