Construction Updates,
July 2024

Update as on 3rd July 2024

Zenith & Zodiac - Complete OC received

Avior, Acrux ,Ion , Vega - OC till 30th Floor

Atlas and Aura - OC till 29th floor

Altis - OC till 31st floor

Phase 1

ZENITH 100%
ZODIAC 100%
ACRUX 100%
ALTIS 100%
ANTILIA 86%
ATLAS 100%
ATRIA 100%
AURA 100%
AVIOR 100%
ION 100%
TRITON 95%
VEGA 100%

Phase 2

CEDAR 93%
DAFFODIL 86%
BODHI 78%
ASTER 56%

% mentioned above is the current demand due as per the construction linked payment schedule

OC received

OC received

Completed work up to Terrace slab level

OC received till 30th floor

Completed work up to Terrace slab level

OC received till 30th Floor.

Finishing work & RCC completed

OC received till 31st Floor.

Completed work up to Terrace slab level

OC received till 29th floor

Completed work up to Terrace slab level

OC received till 29th floor

Completed work up to Terrace slab level

OC received till 30th Floor.

RCC work completed

OC received till 26th floor

Superstructure RCC work completed up to terrace slab.

Block work 85% completed, flat flooring work in progress.

Gypsum & Cement plaster from 2nd to 30th floor completed.

MS railing work 80% done, and door/shutter polishing and window rough ground in progress across multiple floors

Waterproofing up to the 27th floor, kitchen platform work up to the 27th floor, and fire fighting installation 90% completed.

Substructure RCC work completed, flat flooring 100% done across all floors.

Toilet flooring from 1st to 30th floor and external painting up to terrace level completed.

Plumbing concealed work up to the 30th floor and door frame making across all floors finished.

Flat window frames and shutters are 95% installed, the remaining work is in progress

Tiling work is underway across multiple floors.

Fire fighting installation is 100% complete, lift handover/fixing preparation work is ongoing for L1, L2, L3, and L4 lifts to the 30th floor.

RCC work completed.

OC received till 30th Floor

Flat finishing work completed up to 31st floor.

Lift work & fire fighting installation work completed.

220 flat possession handover.

Superstructure RCC 28th slab completed

Ground to 28th floor RCC structure complete

Blockwork, flooring and plastering up to the 27th floor are finished.

Internal plumbing and kitchen platform completed till the 27th floor

Life installation is 75% complete, fire fighting system installed. 

External painting and terrace water proofing nearly complete

 

 

RCC work completed

Superstructure RCC slab completed

Waterproofing done up to 27th floor

Balcony railing work finished from the 4th to the 27th floor (100% completion in ducts).

Block work 100% completed for floors 1st to 27th

Concealed plumbing finished up to the 27th floor.

Staircase flooring completed till 27th floor.

 

Superstructure RCC 28th floor slab completed

Superstructure RCC completed up to the 28th floor, including foundation and plinth slab.

Ground floor work is fully completed.

Flat flooring completed till 11th & 12th floor work in progress.

Block work completed 

Concealed plumbing finished till the 18th floor

Gypsum plaster work completed till the 18th floor.

Superstructure RCC 14th floor slab completed

Superstructure RCC slab completed up to 14th floor; 15th floor 70% completed.

Substructure RCC foundation and column till LG fully completed.

Backfilling and grad slab done till LG level

Plinth checking completed; ground floor slab casted

Amenities work in progress

Swimming pool work 100% completed.

Kids play area 100% work completed.

Clubhouse work in progress. ( 60% completed & functional ) 

TOWER
FLOOR DETAILS
DETAILED UPDATES
Zenith
Completed
OC received
Zodiac
Completed
OC received
Acrux
Completed work up to Terrace slab level
Part OC received till 24th floor

RCC work complete till terrace slab

Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor

Door & shutter polish completed till the 31st floor & single coat polish done on above floors.

Cp & sanitary Flat completed till the 31st floor

Stair case – flooring & skirting completed till B2 To 31st floors

Stair case – window work completed till the terrace

Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor

Entrance lobby work completed

Society office work completed

External Painting work completed till the 24 th floors & 25th to 31st 95% completed.

Terrace water proofing completed & flooring work done 70%

Concealed plumbing work completed from 1st to 31st floor

Fire fighting Delivery material & installation work completed B2 to 31st floor

Fire alarm work completed B2 to 31st floor. testing & commissioning completed

Lift completed from B2 to 31st floor ( 4 nos )
Ion
Completed work up to Terrace slab level
RCC completed till terrace floor



Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 1st to 31st floor completed , door frames main door 1st to 31st and block work toilet 1st to 31st floor 100% completed

External painting putty , primer, texture base completed from basement 1st to terrace in flat 01,02,05,06,07,08 100 % .Flat 3 & 4 work in progress

Plumbing Duct & Open duct Painting-100% completed


Lift 100% completed basement to 31st floor


Fire fighting installation 100% completed
Avior
Completed work up to Terrace slab level
Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor

Stair case work completed from b2 to 31st floor

Entrance lobby work completed

Lift lobby completed till the 31st floor & painting work completed till 31st floor

Refuge floor completed

Stilt floor work completed

Electrification service completed till 31st floor

Plumbing service completed in flat & servant toilet work completed till the 31st floor.

Fire fighting completed B2 to 31st floors & handover to facility

Lift all completed from B2 to 31st
Vega
Completed work up to Terrace slab level
RCC completed till terrace floor,

1st floor to 31st floor Conceal plumbing work completed

Waterproofing 1st to 31st Floor completed

1st to 31st floor 100% completed (Ledge wall)

External painting texture work 90% completed

Lift 70% completed

Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed

Terrace water proofing 100% completed
Antilia
Excavation completed
Foundation work 100% completed , plinth slab 100% completed. Stilt slab 100% completed , 1st Slab 100% completed
Aura
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC work completed till terrace level

Possession flat 103 done

Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing

Painting work 1st to 30th 100% completed

External painting 1st to 30th floor 100% completed stilt painting 85% completed

Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor
Atlas
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 120 done

External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100%

Terrace water proofing completed & flooring work done 90%

Concealed plumbing completed 100%

Fire fighting installation B1 & b2 building from 1st to 30th floor completed

Lift 100% completed

Entrance lobby , society office , stair case , lift lobby completed 100%
Triton
Substructure RCC work completed
UGWT RCC completed

Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed
Altis
Finishing work & RCC completed
RCC completed till terrace floor

Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed

Door frame fixing work completed till 32nd floor 100% completed

Lift L1,L2.L3,L4 100% completed basement to 32nd floor

Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed
Cedar
Excavation completed
Substructure RCC work ground floor slab 103.75mm completed

UGWT completed

Superstructure RCC work upto 4th floor completed.5th floor 50% completed.
Atria
RCC work completed
Substructure RCC work completed

Flat finishing work 5% completed , UGWT , Superstructure RCC work , OHWT & LMR work completed