Construction Updates,
December 2024
Update as on 6th December 2024
PHASE 1
ZENITH, ZODIAC, ACRUX, ALTIS, ATLAS, ATRIA, AURA, AVIOR, ION, VEGA, TRITON, VEGA
ANTILIA
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On or before Possession
| 7% | 31/01/25 |
Superstructure RCC work completed up to terrace slab.
Block work 100% completed, flat flooring work completed till 30th floor.
Gypsum & Cement plaster from 2nd to 30th floor completed.
MS railing work 97% done, and door/shutter polishing and window rough ground in progress across multiple floors
Waterproofing up to the 30th floor, kitchen platform work up to the 30th floor, and fire fighting installation 100% completed.
External painting work 85% completed
Lift work 75% completed
PHASE 2
CEDAR
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On or before Possession
| 7% | will be updated soon |
Superstructure RCC 28th slab completed
Ground to 28th floor RCC structure complete
Blockwork, flooring and plastering up to the 27th floor are finished.
Internal plumbing and kitchen platform completed till the 27th floor
External Painting work completed.
Lift installation is 75% complete, fire fighting system installed.
Terrace water proofing work completed .
DAFFODIL
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On or before Possession
| 7% | Will be updated soon |
RCC work completed
Superstructure RCC slab completed
Waterproofing done up to 27th floor
Balcony railing work finished from the 4th to the 27th floor (100% completion in ducts).
Block work 100% completed for floors 1st to 27th
Concealed plumbing finished up to the 27th floor.
Staircase flooring completed till 27th floor.
Fire fighting installation & alarm work 100% completed
BODHI
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On Flat / Premises Completion
| 8% | 15/01/25 – 28/02/25 |
On possession
| 7% | Will be updated soon |
Superstructure RCC 28th floor slab completed
Superstructure RCC completed up to the 28th floor, including foundation and plinth slab.
Ground floor work is fully completed.
Flat flooring completed till 25th floor .
Block work completed
Concealed plumbing finished till the 27th floor
Gypsum plaster work completed till the 27th floor.
Door frame work completed till 22nd floor.
Fire fighting installation work 70% completed
Lift preparation work in progress
ASTER
Upcoming Milestone | Due | Tentative Date |
---|---|---|
On or after initiation of Internal Work/Brickwork/Plumbing / Premises
| 8% | 25/12/24 – 30/03/25 |
On or after initiation of Lift-Stair lobby,etc (E)
| 7% | 15/01/25 – 12/04/25 |
On or after initiation of Electrical / Painting of the flat / Premises
| 8% | 20/01/25 – 20/04/25 |
On Flat / Premises Completion | 3% | 30/06/25 – 30/07/25 |
On possession | 4% | Will be updated soon |
Superstructure RCC 27th floor slab completed
Superstructure RCC slab completed up to 27th floor; 28 floor 60% completed.
Substructure RCC foundation and column till LG fully completed.
Backfilling and grad slab done till LG level
Plinth checking completed; ground floor slab casted
Block work completed till 14th floor
Flat flooring, kitchen platform work in progress.
Gypsum plaster work 70% completed till 7th floor
concealed plumbing work completed till 9th floor.
% mentioned above is the current demand due as per the construction linked payment schedule. The timeline for upcoming milestone mentioned above is tentative & only provide to enable better cash flow planning for customers. Actual timelines may vary as per site conditions.
AMENTIES
Swimming pool work 100% completed.
Kids play area 100% work completed.
Clubhouse work in progress. ( 75% completed & functional )