Construction Updates,
April 2022

Update as on 6th April, 2022

Zenith & Zodiac - Complete OC received

Altis, Avior, Acrux - OC till 24th Floor

Atlas and Aura - OC till 20th floor

Phase 1

ZENITH 100%
ZODIAC 100%
ACRUX 95%
ALTIS 95%
ANTILIA
37%
ATLAS 95%
ATRIA 78%
AURA 95%
AVIOR 95%
ION 90%
TRITON 70%
VEGA 90%

Phase 2

CEDAR
56%
DAFFODIL
35%
BODHI
35%

% mentioned above is the current demand due as per the construction linked payment schedule

OC received

OC received

Completed work up to Terrace slab level

Part OC received till 24th floor

RCC work complete till terrace slab

Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor

Door & shutter polish completed till the 31st floor & single coat polish done on above floors.

Cp & sanitary Flat completed till the 31st floor

Stair case – flooring & skirting completed till B2 To 31st floors

Stair case – window work completed till the terrace

Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor

Entrance lobby work completed

Society office work completed

Terrace water proofing completed & flooring work done.

Concealed plumbing work completed from 1st to 31st floor

Fire fighting Delivery material & installation work completed B2 to 31st floor

Fire alarm work completed B2 to 31st floor. testing & commissioning completed

Lift completed from B2 to 31st floor ( 4 nos )

Completed work up to Terrace slab level

Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor

Stair case work completed from b2 to 31st floor

Entrance lobby work completed

Lift lobby completed till the 31st floor & painting work completed till 31st floor

Refuge floor completed

Stilt floor work completed

Electrification service completed till 31st floor

Plumbing service completed in flat & servant toilet work completed till the 31st floor.

Fire fighting completed B2 to 31st floors & handover to facility

Lift all completed from B2 to 31st

Finishing work & RCC completed

RCC completed till terrace floor

Flat finishing work completed 

Door frame fixing work completed till 32nd floor 100% completed

Lift L1,L2.L3,L4 100% completed basement to 32nd floor

Fire fighting installation done till 32nd floor  completed

Completed work up to Terrace slab level

Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 139 done

External painting 1st to 30th floor completed, ventilation 100% completed stilt painting 80 % completed, duct & duct pipe painting completed 100%

Terrace water proofing completed & flooring work completed 100 %.

Concealed plumbing completed 100%

Fire fighting installation B1 & b2 building from 1st to 30th floor completed

Lift 100% completed

Entrance lobby , society office , stair case , lift lobby completed 100

Completed work up to Terrace slab level

Part OC received till 20th floor

RCC work completed till terrace level

Possession flat 106 done

Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing

Painting work 1st to 30th 100% completed

External painting 1st to 30th floor 100% completed stilt painting 85% completed, duct & Duct pipe painting 100% completed.

Concealed plumbing work completed from 1st to 30th floor.

Fire fighting testing & commissioning 1st to 30th floor 100% completed.

Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor

RCC work completed

Substructure RCC work completed

North & South side Expansion Joints work completed .

UGWT , Superstructure RCC work , OHWT & LMR work completed

Flat flooring work 3rd To 14th floor work completed , Toilet flooring 3rd to 12th floor work completed.

Kitchen Platform 3rd to 26th floor work completed.

External Painting south side 100% work completed and North side 80% work completed.

Fire Fighting delivery of material & installation 1st to 30th Floor 100% work completed.

Toilet & kitchen water proofing 3rd to 20th floor completed.

Lift 1 ,2,3,4 cabling , hoist beam completed.

Completed work up to Terrace slab level

RCC completed till terrace floor

Conceal Plumbing work 1st to 31st floor 100% completed 1st floor work in progress ,Kitchen platform 1st to 31st floor completed, door frames main door 1st to 31st completed and block work toilet 1st to 31st floor 100% completed.

External Painting putty, primer, texture base Completed from basement 1 to terrace in flat 01,02,,05,06,07,08-100%. 

Plumbing Duct & Open duct Painting-100% completed.

Door & shutter polish work 1st to 20th floor 95% completed.


Lift 100% completed basement to 31st floor.

Flat window 1st To 29th floor 80% completed .

Flat aluminium railing 1st to 20th floor 100%  completed .


Fire fighting installation 100% completed.

Work up to Terrace slab level

RCC completed till terrace floor,

1st floor to 31st floor Conceal plumbing work completed.

Door frame 1st to 31st floor 100% completed.

Water proofing 1st to 31st floor completed.

External painting texture work 100% completed.

Flat aluminium railing 1st to 25th floor 100% completed.

Lift 90% completed.

Concealed plumbing 1st to 31st floor 100% completed.

Fire fighting installation,fire alarm ,testing & commissioning completed 100 %

Terrace water proofing 100% complete

Substructure RCC work completed

UGWT RCC completed

Superstructure RCC Work 100% completed.

Expansion joint RCC work 100 % completed.

Gypsum plaster 25% completed.

Block work 50% completed.

 

Excavation completed

Foundation work 100% completed, Plinth slab 100% completed, Stilt slab 100% completed, 1st slab 100% completed.

UGWT RCC work 100% completed.

Superstructure RCC work- 2nd slab 100% completed.

Excavation completed

Substructure RCC Work  –  Ground floor slab ( 103.75m) completed.

Superstructure RCC work upto 12th slab completed-100%. 13th slab 35 % completed

UGWT completed.

OGT & OHWT water proofing 20% completed.

Excavation completed

Footing completed

Tie beams (+95.85m) level completed 100%  Lower ground level (+99.10M ) tie beams completed 100% 

Back-filling till LG level  100% completed.

Ground floor slab (+103.30M) completed 100%. 

Lightweight filing on ground floor completed

plinth CC work is in progress.

UGWT 100 % completed.

Excavation 100% done

Foundation work 80% completed.

TOWER
FLOOR DETAILS
DETAILED UPDATES
Zenith
Completed
OC received
Zodiac
Completed
OC received
Acrux
Completed work up to Terrace slab level
Part OC received till 24th floor

RCC work complete till terrace slab

Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor

Door & shutter polish completed till the 31st floor & single coat polish done on above floors.

Cp & sanitary Flat completed till the 31st floor

Stair case – flooring & skirting completed till B2 To 31st floors

Stair case – window work completed till the terrace

Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor

Entrance lobby work completed

Society office work completed

External Painting work completed till the 24 th floors & 25th to 31st 95% completed.

Terrace water proofing completed & flooring work done 70%

Concealed plumbing work completed from 1st to 31st floor

Fire fighting Delivery material & installation work completed B2 to 31st floor

Fire alarm work completed B2 to 31st floor. testing & commissioning completed

Lift completed from B2 to 31st floor ( 4 nos )
Ion
Completed work up to Terrace slab level
RCC completed till terrace floor



Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 1st to 31st floor completed , door frames main door 1st to 31st and block work toilet 1st to 31st floor 100% completed

External painting putty , primer, texture base completed from basement 1st to terrace in flat 01,02,05,06,07,08 100 % .Flat 3 & 4 work in progress

Plumbing Duct & Open duct Painting-100% completed


Lift 100% completed basement to 31st floor


Fire fighting installation 100% completed
Avior
Completed work up to Terrace slab level
Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor

Stair case work completed from b2 to 31st floor

Entrance lobby work completed

Lift lobby completed till the 31st floor & painting work completed till 31st floor

Refuge floor completed

Stilt floor work completed

Electrification service completed till 31st floor

Plumbing service completed in flat & servant toilet work completed till the 31st floor.

Fire fighting completed B2 to 31st floors & handover to facility

Lift all completed from B2 to 31st
Vega
Completed work up to Terrace slab level
RCC completed till terrace floor,

1st floor to 31st floor Conceal plumbing work completed

Waterproofing 1st to 31st Floor completed

1st to 31st floor 100% completed (Ledge wall)

External painting texture work 90% completed

Lift 70% completed

Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed

Terrace water proofing 100% completed
Antilia
Excavation completed
Foundation work 100% completed , plinth slab 100% completed. Stilt slab 100% completed , 1st Slab 100% completed
Aura
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC work completed till terrace level

Possession flat 103 done

Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing

Painting work 1st to 30th 100% completed

External painting 1st to 30th floor 100% completed stilt painting 85% completed

Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor
Atlas
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 120 done

External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100%

Terrace water proofing completed & flooring work done 90%

Concealed plumbing completed 100%

Fire fighting installation B1 & b2 building from 1st to 30th floor completed

Lift 100% completed

Entrance lobby , society office , stair case , lift lobby completed 100%
Triton
Substructure RCC work completed
UGWT RCC completed

Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed
Altis
Finishing work & RCC completed
RCC completed till terrace floor

Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed

Door frame fixing work completed till 32nd floor 100% completed

Lift L1,L2.L3,L4 100% completed basement to 32nd floor

Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed
Cedar
Excavation completed
Substructure RCC work ground floor slab 103.75mm completed

UGWT completed

Superstructure RCC work upto 4th floor completed.5th floor 50% completed.
Atria
RCC work completed
Substructure RCC work completed

Flat finishing work 5% completed , UGWT , Superstructure RCC work , OHWT & LMR work completed