Construction Updates,
February 2023

Update as on 2nd February, 2023

Zenith & Zodiac - Complete OC received

Avior, Acrux ,Ion , Vega - OC till 30th Floor

Atlas and Aura - OC till 29th floor

Altis - OC till 31st floor

Phase 1

ZENITH 100%
ZODIAC 100%
ACRUX 100%
ALTIS 100%
ANTILIA 65%
ATLAS 100%
ATRIA 95%
AURA 100%
AVIOR 100%
ION 100%
TRITON 85%
VEGA 100%

Phase 2

CEDAR 70%
DAFFODIL 56%
BODHI 42%
ASTER 20%

% mentioned above is the current demand due as per the construction linked payment schedule

OC received

OC received

Completed work up to Terrace slab level

OC received till 30th floor

Flat finishing work completed.

Common area finishing work completed.

Terrace water proofing completed .

Fire fighting & lift installation work completed.

Completed work up to Terrace slab level

OC received till 30th Floor.

RCC work complete till terrace slab.

Flat finishing work completed . 

Common area finishing work completed.

Entrance lobby work completed

Lift lobby completed.

Refuge floor completed

Electrification service completed upto 31st floor.

Fire fighting work completed .

Lift all completed from B2 to 31st

Finishing work & RCC completed

OC received till 31st Floor.

Flat finishing work completed .

Lift & fire fighting installation work completed.

Completed work up to Terrace slab level

OC received till 29th floor

Flat finishing completed.

Possession flat handover started.

Common area finishing & External painting work completed.

Terrace water proofing completed.

Fire fighting installation & lift work completed.

Entrance lobby , society office , stair case & lift lobby completed .

Completed work up to Terrace slab level

OC received till 29th floor

Flat finishing completed.

Common area finishing & painting work completed.

Fire fighting  & Lift installation work completed.

RCC work completed

Flat flooring work completed.

Kitchen Platform work  completed.

Door frame completed.

Entrance lobby work completed.

External Painting completed.

Fire Fighting work completed.

Terrace water proofing completed.

Lift work completed.

RCC work completed.

OC received till 30th Floor

Flat finishing work completed up to 31st floor.

Water proofing completed up to 31st floor.

External painting texture work completed.

Flat aluminium railing work completed.

Lift work & fire fighting installation work completed.

Terrace water proofing 100% complete

Completed work up to Terrace slab level

OC received till 30th Floor

Flat finishing work completed up to 31st floor.

External Painting completed.

Electrification service completed.


Lift 100% completed basement to 31st floor.

Terrace water proofing work 100% completed.


Fire fighting installed

Superstructure RCC work completed up to 26th slab.

Substructure RCC work – Foundation , plinth slab stilt work 100% completed, 1st slab 100 % completed .

Superstructure RCC work completed up to 26th slab.

Substructure RCC work completed

Flat flooring work completed 90% 

Toilet flooring completed from 2nd to 30th floor.

External painting work completed 1st floor to terrace ( 90% )

Plumbing concealed work completed up to 30th floor.

Door frame making work completed till 30th floor.

Flat window work in progress, frame fixing completed from 5th to 16th floor.

Tiling work in progress.

L1, L2 & L3 Lift handover and L3 lift fixing preparation work in progress up to 20th floor.

Superstructure RCC 28th slab completed

Substructure RCC Work  Ground floor slab completed.

Superstructure RCC work completed up to 28th slab, 

Block work completed upto 23rd floor 100% completed & 24th to 25th floor work in progress.

Gypsum plaster completed upto 16th floor .

Cement plaster completed upto 18th floor.

Substructure RCC 16th floor slab completed

Substructure RCC 16th column and beam steel completed, shuttering completed.

Reinforcement work in progress on 17th floor (35%)

Heritable cc checking done  from CIDCO

Superstructure RCC 3rd floor slab completed

Foundation work  & Plinth slab completed.

Ground floor work 100% completed .

Superstructure RCC 3rd floor slab completed, 4th slab in progress ( 70% )

Excavation work 100% completed.

Footing 50% completed.

Amenities work in progress

Swimming pool work 100% completed.

Kids play area 100% work completed.

Clubhouse work in progress.

TOWER
FLOOR DETAILS
DETAILED UPDATES
Zenith
Completed
OC received
Zodiac
Completed
OC received
Acrux
Completed work up to Terrace slab level
Part OC received till 24th floor

RCC work complete till terrace slab

Flooring , Skirting , dado , kitchen platform, window roughground, toilet basin counter , plumbing work, water proofing , gypsumplaster, cement plaster, painting ,ms railing , Door frame ,Door shutter,door hardwares , Window , block work , flat alumium railing completed till the 31st floor

Door & shutter polish completed till the 31st floor & single coat polish done on above floors.

Cp & sanitary Flat completed till the 31st floor

Stair case – flooring & skirting completed till B2 To 31st floors

Stair case – window work completed till the terrace

Lift lobby flooring , Dado, Architrave , plaster, painting , flase ceiling ,door ,window work completed till the 31st floor

Entrance lobby work completed

Society office work completed

External Painting work completed till the 24 th floors & 25th to 31st 95% completed.

Terrace water proofing completed & flooring work done 70%

Concealed plumbing work completed from 1st to 31st floor

Fire fighting Delivery material & installation work completed B2 to 31st floor

Fire alarm work completed B2 to 31st floor. testing & commissioning completed

Lift completed from B2 to 31st floor ( 4 nos )
Ion
Completed work up to Terrace slab level
RCC completed till terrace floor



Conceal Plumbing work 2nd to 31st floor 100% completed, kitchen platform 1st to 31st floor completed , door frames main door 1st to 31st and block work toilet 1st to 31st floor 100% completed

External painting putty , primer, texture base completed from basement 1st to terrace in flat 01,02,05,06,07,08 100 % .Flat 3 & 4 work in progress

Plumbing Duct & Open duct Painting-100% completed


Lift 100% completed basement to 31st floor


Fire fighting installation 100% completed
Avior
Completed work up to Terrace slab level
Part OC received till 24th Floor

RCC work complete till terrace slab

Flat finishing work completed . Flooring , Skirting , dado , kitchen platform , window, toilet basin counter ,water proofing , gypsum plaster , cement plaster , painting , ms railing ,flat door frames this work done till the 31st floor

Stair case work completed from b2 to 31st floor

Entrance lobby work completed

Lift lobby completed till the 31st floor & painting work completed till 31st floor

Refuge floor completed

Stilt floor work completed

Electrification service completed till 31st floor

Plumbing service completed in flat & servant toilet work completed till the 31st floor.

Fire fighting completed B2 to 31st floors & handover to facility

Lift all completed from B2 to 31st
Vega
Completed work up to Terrace slab level
RCC completed till terrace floor,

1st floor to 31st floor Conceal plumbing work completed

Waterproofing 1st to 31st Floor completed

1st to 31st floor 100% completed (Ledge wall)

External painting texture work 90% completed

Lift 70% completed

Fire fighting installation 100% completed, plinth slab 100% completed, testing and commissioning 100% completed

Terrace water proofing 100% completed
Antilia
Excavation completed
Foundation work 100% completed , plinth slab 100% completed. Stilt slab 100% completed , 1st Slab 100% completed
Aura
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC work completed till terrace level

Possession flat 103 done

Flat finishing completed 100% 1st to 30th floor, flooring , kitchen platform , window , plumbing work , door fittings , flat aluminium railing

Painting work 1st to 30th 100% completed

External painting 1st to 30th floor 100% completed stilt painting 85% completed

Lift 100% completed L1 , L2, L3,L4 – Lb to 30th floor
Atlas
Completed work up to Terrace slab level
Part OC received till 20th floor

RCC completed till terrace floor

Flat finishing completed 100%

Possession flat – 120 done

External painting 1st to 30th floor completed, ventilation 100% completed, stilt painting 80 % completed, duct & duct pipe painting completed 100%

Terrace water proofing completed & flooring work done 90%

Concealed plumbing completed 100%

Fire fighting installation B1 & b2 building from 1st to 30th floor completed

Lift 100% completed

Entrance lobby , society office , stair case , lift lobby completed 100%
Triton
Substructure RCC work completed
UGWT RCC completed

Superstructure RCC work below OHT bottom slab work completed , Parapet wall completed
Altis
Finishing work & RCC completed
RCC completed till terrace floor

Flat finishing work completed , Flooring, skirting, toilet flooring , toilet dado, kitchen platform, window work completed till 32nd floor, 100% painting work done till 25th floor and 26th to 32nd floor coat paint completed

Door frame fixing work completed till 32nd floor 100% completed

Lift L1,L2.L3,L4 100% completed basement to 32nd floor

Fire fighting installation done till 32nd floor ,Fire alarm & testing ,commissioning done till 25th floor & 26th to 32nd floor 100% work completed
Cedar
Excavation completed
Substructure RCC work ground floor slab 103.75mm completed

UGWT completed

Superstructure RCC work upto 4th floor completed.5th floor 50% completed.
Atria
RCC work completed
Substructure RCC work completed

Flat finishing work 5% completed , UGWT , Superstructure RCC work , OHWT & LMR work completed

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.