Construction Updates – June 2020
Construction Updates – June 2020
Atlas & Aura - OC till 20th floor
Altis, Avior, Acrux - OC till 24th Floor
Zenith & Zodiac - Complete OC received
Atlas & Aura - OC till 20th floor
Altis, Avior, Acrux - OC till 24th floor
Zenith & Zodiac - Complete OC received.
Nexzone now has Occupation Certificate for 7 towers out of 12 in Phase 1. Construction has resumed with in-situ labor & we are confident of delivering the remaining towers according to plan.
TOWER | FLOOR DETAILS | DETAILED UPDATES |
---|---|---|
Zenith | Completed | OC received |
Zodiac | Completed | OC received |
Altis | Completed work up to Terrace slab level | Part OC received till 24th Floor, RCC work complete till terrace slab, Internal Civil work completed, Internal Tiling work initiated form 25th floor, Toilet waterproofing & conceal plumbing completed up to 31st floor, all 4 lifts completed |
Avior | Completed work up to Terrace slab level | Part OC received till 24th Floor, RCC work complete till terrace slab, Internal Civil work completed, Internal Tiling work completed upto 31st floor except 27th floor, Toilet Conceal plumbing work completed upto 31st floor, toilet waterproofing work completed upto 31st floor except 27th floor, all 4 lifs completed |
Acrux | Completed work up to Terrace slab level | Part oc received till 24th floor, RCC work complete till terrace slab, Internal civil work completed upto 31st floor, 25th & 26th floor tiling completed, Conceal plumbing work in progress above 25th floor , |
Atlas | Completed work up to Terrace slab level | OC received till 20th floor RCC work completed till terrace level, Tiling work Completed till 25th floor, All finishing activity completed upto 20th floor, Fire fighting, FAPA completed upto 30th floor, 3 lifts work completed |
Aura | Completed work up to Terrace slab level | OC received till 20th floor RCC work completed till terrace level, Tiling work Completed till 25th floor, All finishing activity completed upto 20th floor, Fire fighting,FAPA completed upto 30th floor, 4 lifts work completed |
Ion | Completed work up to Terrace slab level | RCC completed till terrace floor, Conceal Plumbing completed up to 31st floor except 1st & 2nd floor, toilet water proofing complete upto 26th floor except 1st & 2nd floor, 75% external texture paint work completed, door frame fixing work initiated form 4th floor, 3 lifts work completed |
Vega | Completed work up to Terrace slab level | RCC completed till terrace floor, Conceal Plumbing completed upto 23rd floor except 1st & 2nd floor, toilet water proofing complete upto 7th floor except 1st & 2nd floor, External texture paint work has initiated, 1 lift is ready, 3 lift installation WIP, |
Atria | Completed work up to Terrace slab level | RCC completed till terrace slab |
Triton | Completed RCC work up to 22nd Slab level | RCC work completed up to 22nd Slab level |
Antilia | Foundation | Initiated work for foundation |