Construction Updates – Oct 2019

Construction Updates – Oct 2019

OC received for the first 4 towers till the 23rd floor

With 10 towers having already completed till the terrace slab, we are in a strong position to deliver the remaining towers according to plan. Altis and Avior P+23rd floor OC has been received.

Previous
Next
TOWER
FLOOR DETAILS
DETAILED UPDATES
Zenith
Completed work up to Terrace slab level

Complete OC received

Zodiac
Completed work up to Terrace slab level

Complete OC received

Altis
Completed work up to Terrace slab level

Part OC received till 24th Floor

RCC work complete till terrace slab

Internal Civil work completed

Avior
Completed work up to Terrace slab level

Part OC received till 24th Floor

RCC work complete till terrace slab

Internal Civil work completed

Acrux
Completed work up to Terrace slab level

OC received till 24th Floor

RCC work complete till terrace slab

Internal Civil work initiated from 26th floor onwards

Atlas
Completed work up to Terrace slab level

RCC work completed till terrace level

Tiling work Completed till 24th floor except the 1st floor

Aura
Completed work up to Terrace slab level

RCC work completed till terrace level

Tiling work Completed till 24th floor

Ion
Completed work up to Terrace slab level

RCC completed till terrace floor

Plumbing and water proofing started

70% external paint work is done

Vega
Completed work up to Terrace slab level

RCC completed up to Terrace slab level

Plumbing and water proofing started
Atria
Completed work up to Terrace slab level

RCC completed till terrace slab

Internal civil work initiated
Triton
Completed RCC work up to 15th Slab level
RCC work completed up to 15th Slab level
Antilia
Foundation
Initiated work for foundation