Construction Updates,
July 2026
Update as on 2nd July 2026
PHASE 1 – 12 Towers Delivered
ZENITH, ZODIAC, ACRUX, ALTIS, ATLAS, ATRIA, AURA, AVIOR, ION, VEGA, TRITON, ANTILIA
PHASE 2
CEDAR , DAFFODIL
OC RECEIVED
BODHI
Milestone | Due | Tentative Date |
|---|---|---|
Due | 93% | NA |
On Possession | 7% | Will be updated soon |
The entire RCC structure, including the 28th floor slab and terrace slab, is fully completed — along with the foundation and plinth.
Ground floor work is fully finished.
Inside the homes, flooring is completed till the 27th floor, making the interiors feel almost move-in ready.
Wall work is 100% done, with smooth gypsum plaster finishing completed till the 27th floor.
Concealed plumbing lines are also finished up to the 27th floor.
Door frames are already in place till the 27th floor, and door hardware installation (locks, handles, etc.) is now in progress.
Windows are 100% installed, with balance work ongoing.
Tiling work inside homes is completed, adding the final touches to the interiors.
Firefighting system installation is 100% done, and the Chief Fire Officer’s inspection is scheduled soon.
Lift installation is in progress, ensuring smooth connectivity across all floors.
ASTER
Milestone | Due | Tentative Date |
|---|---|---|
Due | 93% | NA |
On Flat / Premises Completion / on possession | 3% | Will update soon |
The entire RCC structure is complete up to the 28th floor, including the terrace slab. Foundation, columns, and plinth work are also fully done.
Blockwork (internal walls) is complete till the 28th floor, shaping the homes across the tower.
Gypsum plastering is completed till the 28th floor.
Flooring and kitchen platforms are in progress — tiling work is finished up to the 28th floor and Kitchen platform work till 28th floor completed
Waterproofing is done till the 28th floor
Plumbing (CPVC concealed lines) is fully completed, ensuring proper water supply and drainage.
Firefighting systems are installed till the 28th floor.
Lift installation is almost done, with the final brackets now being installed.
Staircase tiling is completed, and painting work across the tower is 98% completed
PHASE 3 – NIRVANA
NIRVANA TOWER A
Milestone | Due |
|---|---|
On booking | 10% |
Excavation Work 99% completed
Footing & column reinforcement binding work completed 95% , Footing casting completed 100%, Column casting till tie beam completed 100% , Plinth beam pic 95% , Plinth beam reinforcement work 90 % completed & plinth casting 90%
NIRVANA TOWER B
Milestone | Due |
|---|---|
On booking | 10% |
Excavation Work 100% completed
Footing & column reinforcement binding work completed 100% , Footing casting completed till plinth beam 100%, Shuttering work in progress
NIRVANA TOWER C
Milestone | Due |
|---|---|
On booking | 10% |
Excavation Work 100% completed
footing casting completed 80%, Column work till tie beam 70%, shuttering work completed 40%
NIRVANA TOWER D
Milestone | Due |
|---|---|
On booking | 10% |
Excavation Work 55% completed
AMENITIES
Swimming Pool, Kids Play Area, Sports Court – Operational
Clubhouse work in progress – 80% completed & functional
% mentioned above is the current demand due as per the construction linked payment schedule. The timeline for upcoming milestone mentioned above is tentative & only provide to enable better cash flow planning for customers. Actual timelines may vary as per site conditions.
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.

















