Construction Updates, July 2023

Update as on 7th July, 2023

Construction Updates, July 2023

Update as on 7th July, 2023

Zaver Aracde
70%

% mentioned above is the current demand due as per the construction linked payment schedule.

Floor Details Detailed Updates

Substructure RCC Work

100 % completed.

Superstructure RCC Work

Terrace slab completed.

Shop Finishing

Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed.

Common Area Finishing

1st floor stair case flooring & skirting work 100% completed.
Blockwork completed till 15th floor.
Water proofing completed till 13th floor.
DG set installation work completed
Habitable Fire fighting work completed till 8th floor.
Car lift 90% installation completed.
Entrance lobby flooring work 100% completed.
Gypsum work completed till 10th floor .

MARATHON REFERRAL AND LOYALTY PROGRAM

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.