Construction Updates, April 2024

Update as on 3rd April, 2024

Construction Updates, April 2024

Update as on 3rd April/span>

Zaver Aracde
75%

% mentioned above is the current demand due as per the construction linked payment schedule.

Floor Details Detailed Updates

Substructure RCC Work

100 % completed.

Superstructure RCC Work

Terrace slab completed.

Shop Finishing

Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed.

Common Area Finishing

Block work 100% completed
Water proofing completed till 16th floor.
DG set installation work completed
Fire fighting work completed.
Lift 1 to 4 commissioning is done
Entrance lobby & Typical lobby flooring ,dodo & facade work 100% completed
Gypsum work completed till 17th floor .

MARATHON REFERRAL AND LOYALTY PROGRAM

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.