Construction Updates, August 2022
Update as on 4th August, 2022
Construction Updates, August 2022
Update as on 4th August, 2022
% mentioned above is the current demand due as per the construction linked payment schedule.
Floor Details | Detailed Updates |
---|---|
Substructure RCC Work |
100 % completed. |
Superstructure RCC Work |
8th floor RCC slab completed & 9th floor RCC slab in progress. |
Shop Finishing |
Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed. |
Common Area Finishing |
1st floor stair case flooring & skirting work 100% completed. 2nd stilt floor work 100% completed. Fire fighting work completed till 1st floor. Car lift 40% work completed. |
Amenities | Updates |
---|---|
Club House |
Plinth beam work 25% completed |