Construction Updates, August 2022

Update as on 4th August, 2022

Construction Updates, August 2022

Update as on 4th August, 2022

Zaver Aracde
41%

% mentioned above is the current demand due as per the construction linked payment schedule.

Floor Details Detailed Updates

Substructure RCC Work

100 % completed.

Superstructure RCC Work

8th floor RCC slab completed & 9th floor RCC slab in progress.

Shop Finishing

Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed.

Common Area Finishing

1st floor stair case flooring & skirting work 100% completed. 2nd stilt floor work 100% completed. Fire fighting work completed till 1st floor. Car lift 40% work completed.

Amenities  Updates

Club House

Plinth beam work 25% completed

MARATHON REFERRAL AND LOYALTY PROGRAM

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.