Construction Updates, February 2024

Update as on 7th February, 2024

Construction Updates, February 2024

Update as on 7th February, 2024

Zaver Aracde
75%

% mentioned above is the current demand due as per the construction linked payment schedule.

Floor Details Detailed Updates

Substructure RCC Work

100 % completed.

Superstructure RCC Work

Terrace slab completed.

Shop Finishing

Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed.

Common Area Finishing

Blockwork completed till 15th floor.
Water proofing completed till 15th floor.
DG set installation work completed
Fire fighting work completed.
Lift 1 & 2 commissioning is done & Lift 3 & 4 work in progress .
Entrance lobby flooring ,dodo & facade work 100% completed.
Gypsum work completed till 16th floor .