Construction Updates, February 2023
Update as on 2nd February, 2023
Construction Updates, February 2023
Update as on 2nd February, 2023
% mentioned above is the current demand due as per the construction linked payment schedule.
Floor Details | Detailed Updates |
---|---|
Substructure RCC Work |
100 % completed. |
Superstructure RCC Work |
18th floor RCC slab completed & 19th slab 40% completed. |
Shop Finishing |
Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed. |
Common Area Finishing |
1st floor stair case flooring & skirting work 100% completed. 2nd stilt floor work 100% completed. Fire fighting work completed till 1st floor. Car lift 60% work completed. Entrance lobby plaster 100% completed. |