Construction Updates, June 2023

Update as on 4th June, 2023

Construction Updates, June 2023

Update as on 4th June, 2023

Zaver Aracde
70%

% mentioned above is the current demand due as per the construction linked payment schedule.

Floor Details Detailed Updates

Substructure RCC Work

100 % completed.

Superstructure RCC Work

Terrace slab completed.

Shop Finishing

Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed.

Common Area Finishing

1st floor stair case flooring & skirting work 100% completed.
Water proofing work in progress.
DG set installation work completed till 2nd floor.
Fire fighting work completed till 1st floor.
Car lift 90% installation completed.
Entrance lobby flooring work 95% completed.
Entrance lobby plaster 100% completed.