Construction Updates, March 2024

Update as on 8th March, 2024

Construction Updates, March 2024

Update as on 8th March, 2024

Zaver Aracde
75%

% mentioned above is the current demand due as per the construction linked payment schedule.

Floor Details Detailed Updates

Substructure RCC Work

100 % completed.

Superstructure RCC Work

Terrace slab completed.

Shop Finishing

Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed.

Common Area Finishing

Block work completed till 17th floor.
Water proofing completed till 16th floor.
DG set installation work completed
Fire fighting work completed.
Lift 1 ,2 & 3 commissioning is done & Lift 4 work in progress .
Entrance lobby flooring ,dodo & facade work 100% completed.
Gypsum work completed till 17th floor .