Construction Updates, November 2022

Update as on 4th November, 2022

Construction Updates, November 2022

Update as on 4th November, 2022

Zaver Aracde
41%

% mentioned above is the current demand due as per the construction linked payment schedule.

Floor Details Detailed Updates

Substructure RCC Work

100 % completed.

Superstructure RCC Work

13th floor RCC slab completed & 14th floor RCC slab 10% completed.

Shop Finishing

Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed.

Common Area Finishing

1st floor stair case flooring & skirting work 100% completed. 2nd stilt floor work 100% completed. Fire fighting work completed till 1st floor. Car lift 60% work completed.