Construction Updates, October 2022
Update as on 6th October, 2022
Construction Updates, October 2022
Update as on 6th October, 2022
% mentioned above is the current demand due as per the construction linked payment schedule.
Floor Details | Detailed Updates |
---|---|
Substructure RCC Work |
100 % completed. |
Superstructure RCC Work |
11th floor RCC slab completed & 12th floor RCC slab 80% completed. |
Shop Finishing |
Flooring, Skirting, Gypsum plaster, Cement plaster, Block work 100 % completed. |
Common Area Finishing |
1st floor stair case flooring & skirting work 100% completed. 2nd stilt floor work 100% completed. Fire fighting work completed till 1st floor. Car lift 60% work completed. |
MARATHON REFERRAL AND LOYALTY PROGRAM
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.