Construction Updates, September 2021.
Construction Updates, September 2021.
Construction Progressing smoothly
Eminence construction is in full swing and we have completed work up to 11 slabs. We have already constructed the Rehab tower till 18 floors. The Sale tower is set to replicate the same pace in terms of construction.
Completion
% mentioned above is the current demand due as per the construction linked payment schedule
Tower | Floor Details | Detailed Updates |
---|---|---|
Sale building | RCC work | Completed till terrace slab  (22nd floor completed) |
Blockwork | 2nd, 5th, 6th, 7th, 8th, 9th, 10th, 11th floor, 12th, 13th, 14th, 16th floor completed | |
Gypsum work | 2nd, 6th, 7th, 8th, 9th, 10th, 11th, 12th completed | |
Sample flat | Sample flat at 2nd floor completed | |
Rehab building | RCC work | RCC- 18th slab completed RCC Center core – OHWT & lift & staircase completed till 22nd floor (100% completed) |
Finishing work (till 16th floor partial handover) | Fire fighting- 100% Internal wall putty- 100% Conceal plumbing- 95% Door frame fixing- 95% Dado Tiling – 100% Flat flooring – 100% Kitchen platform- 100% Waterproofing – 100% Window fixing- 90% External painting – 95% Electrical internal wiring – 90% |