Construction Updates, November 2023.
Construction Updates, November 2023.
OC received till terrace slab !!
Completion
% mentioned above is the current demand due as per the construction linked payment schedule
Tower | Floor Details | Detailed Updates |
---|---|---|
Sale building | RCC work | Completed till terrace slab |
Finishing work | Fire Fighting- 100% Conceal plumbing- 100% kitchen Platform- 100% waterproofing – 100% Lift 1 & 2 installation completed. Flat flooring & window fixing completed from 2nd to 22nd floor Lift lobby flooring completed from 2nd to 22nd floor |
|
Rehab building | RCC work | RCC 100% completed |
Finishing work (completed up to 17th floor ) | Fire fighting- 100% Internal wall putty- 100% Conceal plumbing- 100% Door frame fixing- 100% Dado Tiling – 100% Flat flooring – 100% Kitchen platform- 100% Waterproofing – 100% Window fixing- 100% Lift installation – 100 % External painting – 100% Electrical internal wiring – 100% |
|
Infra | External Work | External paving work 100% completed. |