Construction Updates, June 2023.

Construction Updates, June 2023.

Construction Progressing smoothly

Eminence construction is in full swing and we have completed work till terrace slab. We have already constructed the Rehab tower till 22nd floors. The Sale tower is set to replicate the same pace in terms of construction.

Completion
85%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Floor Details Detailed Updates
Sale building RCC work Completed till terrace slab
Blockwork 1st to 22nd  floor completed
Gypsum work 2nd to 22nd floor  completed
Finishing work Fire Fighting- 100%
Conceal plumbing- 100%
kitchen Platform- 100%
waterproofing – 100%
Lift 1 & 2 installation completed.
Flat flooring & window fixing completed from 2nd to 22nd floor
Lift lobby flooring completed from 2nd to 22nd floor
Rehab building RCC work RCC 100% completed
Finishing work (completed up to 17th floor ) Fire fighting- 100%
Internal wall putty- 100%
Conceal plumbing- 100%
Door frame fixing- 100%
Dado Tiling – 100%
Flat flooring – 100%
Kitchen platform- 100%
Waterproofing – 100%
Window fixing- 100%
Lift installation – 100 %
External painting – 100%
Electrical internal wiring – 100%
Infra External Work External paving work  100% completed.

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.

[index]
[index]