Construction Updates, March 2022.

Construction Updates, March 2022.

Construction Progressing smoothly

Eminence construction is in full swing and we have completed work up to 22nd slabs. We have already constructed the Rehab tower till 22nd floors. The Sale tower is set to replicate the same pace in terms of construction.

Completion
72%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Floor Details Detailed Updates
Sale building RCC work Completed till terrace slab
Blockwork 2nd, 5th, 6th, 7th, 8th, 9th, 10th, 11th floor, 12th, 13th, 14th, 16th, 17th, 18th, 19th floor completed
Gypsum work 2nd, 6th, 7th, 8th, 9th, 10th, 11th, 12th, 13th, 14th, 15th, 16th, 17th, 18th,19th completed
Finishing work Fire Fighting- 50%
Conceal plumbing- 60%
kitchen Platform- 50%
waterproofing – 70%
Fire fighting – 100%
Sample flat Sample flat at 2nd floor completed
Rehab building RCC work RCC 100% completed
Finishing work (till 16th floor partial handover) Fire fighting- 100%
Internal wall putty- 100%
Conceal plumbing- 95%
Door frame fixing- 95%
Dado Tiling – 100%
Flat flooring – 100%
Kitchen platform- 100%
Waterproofing – 100%
Window fixing- 90%
External painting – 95%
Electrical internal wiring – 90%
Infra External Work External paving work  50% completed.