Construction Updates, September 2022.

Construction Updates, September 2022.

Construction Progressing smoothly

Eminence construction is in full swing and we have completed work till terrace slab. We have already constructed the Rehab tower till 22nd floors. The Sale tower is set to replicate the same pace in terms of construction.

Completion
75%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Floor Details Detailed Updates
Sale building RCC work Completed till terrace slab
Blockwork 2nd, 5th, 6th to 22nd  floor completed
Gypsum work 2nd, 6th, 7th to 21st  completed
Finishing work Fire Fighting- 80%
Conceal plumbing- 75%
kitchen Platform- 65%
waterproofing – 80%
Lift 1 installation completed & Lift 2 in progress.
Sample flat Sample flat at 2nd floor completed
Rehab building RCC work RCC 100% completed
Finishing work (completed up to 17th floor ) Fire fighting- 100%
Internal wall putty- 100%
Conceal plumbing- 100%
Door frame fixing- 100%
Dado Tiling – 100%
Flat flooring – 100%
Kitchen platform- 100%
Waterproofing – 100%
Window fixing- 100%
Lift installation – 100 %
External painting – 100%
Electrical internal wiring – 100%
Infra External Work External paving work  80% completed.