Construction Updates, April 2022
Update as on 4th April, 2022
Construction Updates, April 2022
Update as on 4th April, 2022
![nextown_construction-updates_oct-2020_16](https://marathon.in/nextown/wp-content/uploads/sites/6/2020/10/nextown_construction-updates_oct-2020_16.jpg)
% mentioned above is the current demand due as per the construction linked payment schedule.
Tower Name | Detailed Updates |
---|---|
Opal |
OC Received |
Topaz |
OC Received |
Amber |
OC Received |
Emerald |
OC Received |
Coral |
Completed RCC work upto Over Head Water Tank (OWHT) |
Sapphire |
RCC work- 6th slab complted, 7th slab in progress 15% completed. |
![marathon-nextown-dombivli-layout-copy](https://marathon.in/nextown/wp-content/uploads/sites/6/2021/03/marathon-nextown-dombivli-layout-copy.jpg)
Emerald
Possession Date: Dec 2022
OC Received
Sapphire
Possession Date: Jun 2023
RERA No.: P51700001265
Coral
Possession Date: Jun 2023
RERA No.: P51700000952