Construction Updates, January 2024

Update as on 3rd January 2024

Construction Updates, January 2024

Update as on 3rd January, 2024

Sapphire
85%
Ruby
46%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

OC Received 

Sapphire

16th slab RCC completed.
Terrace slab completed.
Flat flooring work completed till 16th floor.
Gypsum plaster work completed till 16th floor for internal flat .
Block work completed up to 16th floor
Conceal plumbing work on wall 1st to 16th floor completed.
Toilet internal drainage work in progress.
Kitchen platform work completed till 14th floor & 16th floor work in progress.
Internal water proofing completed till 16th floor.
Lift installation work completed.
Internal fire fighting work in progress

Ruby

RCC 1st floor slab completed
Footing work , Stub column & plinth beam 100% completed & back filling 100% completed.
Grid slab 100% completed.
Stilt floor column work 100% completed.
Conventional 1st floor slab completed .2nd & 3rd mivan slab completed & 4th slab shuttering work in progress.

Amenities  Updates

Club House

Terrace slab work completed

Sub structure work completed.
1st slab completed
Terrace slab completed
LMR column reinforcement work in progress
Multipurpose court 100% completed.
Internal electrical work completed.

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2024
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
OC Received

Ruby

Possession Date: Dec 2026
RERA No.: P51700021189

Marathon Referral and Loyalty Program

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.