Construction Updates,November 2023

Update as on 5th November 2023

Construction Updates,November 2023

Update as on 5th November, 2023

Sapphire
78%
Ruby
43%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

OC Received 

Sapphire

16th slab RCC completed.
Terrace slab completed.
Flat flooring work completed till 14th floor & 16th floor work in progress.
Gypsum plaster work completed till 14th floor & 16th floor work in progress.
Block work completed up to 16th floor
Conceal plumbing work on wall 1st to 14th floor completed.
Toilet internal drainage work in progress.
Kitchen platform work completed till 14th floor & 16th floor work in progress.
Internal water proofing completed till 16th floor.
Lift lobby flooring work completed till 13th floor.
Stilt floor work in progress.
Internal fire fighting work in progress

Ruby

RCC 1st floor slab completed
Footing work , Stub column & plinth beam 100% completed & back filling 100% completed. Grid slab 100% completed.
Stilt floor column work 100% completed. Conventional 1st floor slab completed & 2nd slab mivan setting work in progress.

Amenities  Updates

Club House

Plinth beam work 100% completed,Back filling 100% completed & Stilt level PCC 100% completed.

Sub structure work completed.
1st slab casting completed & 2nd level slab column 50% completed & remaining work in progress.
Plinth beam completed.
Multipurpose court 100% completed.
Internal electrical work completed.

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2024
RERA No.: P51700001265

Coral

Possession Date: Jun 2023
OC Received

Ruby

Possession Date: Dec 2026
RERA No.: P51700021189