Construction Updates,October 2024

Update as on 3rd October 2024

Construction Updates, October 2024

Update as on 3rd October, 2024

Sapphire
100%
Ruby
70%
Jasper
30%

% mentioned above is the current demand due as per the construction linked payment schedule.

Tower Name Detailed Updates

Opal

OC Received

Topaz

OC Received

Amber

OC Received

Emerald

OC Received

Coral

OC Received 

Sapphire

OC Received 

Ruby

RCC 22nd floor slab completed
Footing work , Stub column & plinth beam & back filling 100% completed.
Grid slab 100% completed.
Stilt floor column work 100% completed.
Superstructure RCC slab completed till 22nd floor & terrace  slab work in progress.
Block floor is completed till 19th floor, 20th floor work in progress.
Gypsum & cement plaster work completed till 14th floor & 15th floor work in progress.

Jasper

construction not commenced yet

Amenities  Updates

Club House

Terrace slab work completed

Sub structure work completed.
1st slab completed
Terrace & roof slab completed
LMR column reinforcement work completed.
Multipurpose court 100% completed.
Internal electrical work completed & block work ground & 1st floor work in progress.
Block work completed on ground & 1st floor , terrace slab work in progress.

Emerald

Possession Date: Dec 2022
OC Received

Sapphire

Possession Date: Jun 2024
OC Received

Coral

Possession Date: Jun 2023
OC Received

Ruby

Possession Date: Dec 2026
RERA No.: P51700021189

Jasper

Possession Date: Dec 2028
RERA No.: P51700049449