Construction Updates, April 2020.

OC received till 15th floor

Lobby and entry passage with external paint completed.

Emblem

Floor Details:
RCC work completed up to 21st floor.

Detailed updates:
16th to 21st floor window works 98% completed
External Painting completed.
18th and above Fire Fighting and blockwork completed
Lift 3 installation completed
Canopy work at ground floor completed
Club House finishing Work in progress