Construction Updates, April 2019.

OC received till 15th floor

Lobby and entry passage almost complete with external paint done till 15th floor

Emblem

Floor Details:
RCC work completed till Terrace slab

Detailed updates:
Finishing works completed for 6 flats,
Waterproofing works completed of 3 floors,
External paint of two elevations completed till the 15th floor,
Lift machine room and over head water tank work in progress