Construction Updates, Nov 2019.

OC received till 15th floor

Lobby and entry passage almost complete with external paint 90% completed.

Emblem

Floor Details:
RCC work completed up to 21st floor.

Detailed updates:
18th to 21st floor window works 90% completed
External Painting 90% complete.
18th and above Fire Fighting and blockwork in progress.
Lift 3 installation work in progress
Canopy work at ground floor 85% complete.

Emblem

Floor Details:
RCC work completed up to 21st floor.

Detailed updates:
18th to 21st floor window works 90% completed
External Painting 90% complete
18th and above Fire Fighting and blockwork in progress
Lift 3 installation work in progress
Canopy work at ground floor 85% complete