Construction Updates – September 2022
Update as on 4th September, 2022
Construction Updates – September 2022
Update as on 4th September, 2022
Tower | Updates |
---|---|
Aura | 35th slab RCC completed. 36th slab RCC work in progress (80% completed) Block work completed till 30th floor. Plumbing Conceal work completed up to 30th Floor. Gypsum work completed up to 29th Floor. Waterproofing completed up to 30th Floor. Electrical Conceal Work in block-work completed up to 30th Floor. Door Frame fixing work completed up to 28th Floor. Window rough ground marble fixing completed up to 27th Floor. Window sill fixing completed up to 27th floor. Tiling & dado were completed up to the 29th floor. Kitchen Platform fixing completed up to 27th floor. Lift Lobby Tiling completed 1st to 27th-floor complete, 28th & 29th-floor work in progress (90% Completed). Staircase tiling 2nd floor to 27th-floor complete, 28th-floor work in progress (90% Completed). Painting primer and base coat putti work completed up to 27th floor. Internal Duct Finishing (40% complete) Service slab Plaster (55% complete) External Plaster (45% Complete) External surface preparation for paint (40% Complete) |
Elara | RCC work up to 36th floor completed. Block work completed till 35th floor. Plumbing Conceal work completed up to 35th Floor. Gypsum work completed up to 33rd Floor. Waterproofing completed up to 35th Floor. Electrical Conceal Work in block-work completed up to 35th Floor. Door Frame fixing work completed up to 29th Floor. Window rough ground marble fixing completed up to 29th Floor. Window sill fixing completed up to 29th floor. Tiling & dado were completed on the 33rd floor. Kitchen Platform fixing completed on 28th floor. Lift Lobby Tiling work completed on 8th floor to 31st floor, 32nd floor work in progress (50% Completed). Staircase tiling 2nd floor to 33rd floor complete Painting primer and base coat putti work completed 2nd floor to 26th floor. Internal Duct Finishing (15% complete) Service slab Plaster (60% complete) External Plaster (20% Complete) External surface preparation for paint (25% Complete) |
Nova | Foundation work completed. Basement work 65% completed. STP tank civil work 50% completed |
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.