Construction Updates – January 2026
Update as on 8th January, 2026
Construction Updates – January 2026
Update as on 8th January, 2025
| Tower | Updates |
|---|---|
| AURA & ELARA | Aura and Elara towers have received Occupancy Certificate (OC) up to the 35th floor |
| Tower | Updates |
|---|---|
| NOVA |
(Under Construction – Significant Progress Made) |
| Structural Progress:
Slab work is completed up to the 24th floor. |
|
| Interior Work:
Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor. Plumbing & Waterproofing: Installed up to the 23rd floor. Gypsum Work: Completed up to the 23rd floor. Kitchen Platforms: Installed up to the 23rd floor. Flooring: Tiling completed up to the 23rd floor. Doors & Frames: Installed up to the 23rd floor. Fire Safety: Firefighting system work completed up to the 23rd floor. |
|
| External & Infrastructure Work:
Surrounding infrastructure work in Progress. Storm water drainage is 97% complete. Basement & underground facilities (such as water tanks and STP) are fully completed. |
| Tower | Updates |
|---|---|
| FLORA |
(Under Construction – Significant Progress Made) |
| Structural Progress:
Slab work is completed up to the 23rd Floor ( 24th slab) & terrace slab work in progress brick work & electric conduit in wall completed till 18th floor Concealed plumbing & waterproofing completed till 12th floor Gypsum work completed till 13th floor Tiling work completed till 6th floor work completed Door frame fixing completed till 12th floor. Fire fighting work completed till 9th floor |
|
| External & Infrastructure Work:
Basement & underground facilities (such as water tanks and STP) are fully completed. Periphery Retaining Wall & Pump Room Construction completed. |