Construction Updates – January 2026

Update as on 8th January, 2026

Construction Updates – January 2026

Update as on 8th January, 2025

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA & ELARA Aura and Elara towers have received Occupancy Certificate (OC) up to the 35th floor
Tower Updates
NOVA

(Under Construction – Significant Progress Made)

Structural Progress:

Slab work is completed up to the 24th floor.

Interior Work:

Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor.

Plumbing & Waterproofing: Installed up to the 23rd floor.

Gypsum Work: Completed up to the 23rd floor.

Kitchen Platforms: Installed up to the 23rd floor.

Flooring: Tiling completed up to the 23rd floor.

Doors & Frames: Installed up to the 23rd floor.

Fire Safety: Firefighting system work completed up to the 23rd floor.

External & Infrastructure Work:

Surrounding infrastructure work in Progress.

Storm water drainage is 97% complete.

Basement & underground facilities (such as water tanks and STP) are fully completed.

Tower Updates
FLORA

(Under Construction – Significant Progress Made)

Structural Progress:

Slab work is completed up to the 23rd Floor ( 24th slab) & terrace slab work in progress

brick work & electric conduit in wall completed till 18th floor

Concealed plumbing & waterproofing completed till 12th floor

Gypsum work completed till 13th floor

Tiling work completed till 6th  floor work  completed

Door frame fixing completed till 12th floor.

Fire fighting work completed till 9th floor

External & Infrastructure Work:

Basement & underground facilities (such as water tanks and STP) are fully completed.

Periphery Retaining Wall & Pump Room Construction completed.

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.