Construction Updates – September 2021

AURA
ELARA
Tower Updates
Aura Detailed updates (Possession – July 2022):
Completed RCC work upto 26th floor, 27th floor RCC work in progress (20 % Completed).
Blockwork completed till 21st floor.
Plumbing Conceal work completed upto 21st Floor.
Gypsum work completed upto 21st Floor.
Waterproofing completed upto 21st Floor.
Electrical Conceal Work in block work completed upto 21st Floor.
Door Frame fixing work completed upto 4th Floor.
Window rough ground marble fixing completed upto 21st Floor.
Window sill fixing completed upto 21st floor.
Tiling & dado completed in 195 Flats..
Kitchen Platform fixing completed in 195 Flats.
Elara Detailed updates (Possession – December 2022):
RCC work upto 28th floor completed. 29th floor RCC work in progress (60 % Completed).th floor completed.
Blockwork completed till 22nd floor.
Plumbing Conceal work completed upto 15th Floor.
Gypsum work completed upto 17th Floor.
Waterproofing completed upto 19th Floor.
Electrical Conceal Work in block work completed upto 19th Floor.
Door Frame fixing work completed upto 2nd Floor.
Window rough ground marble fixing completed upto 2nd Floor.
Window sill fixing completed upto 2nd floor.
Tiling & dado completed upto 13th floor.
Internal Tiling completed upto 3rd floor.