Construction Updates – October 2025
Update as on 6th October, 2025
Construction Updates – October 2025
Update as on 6th October, 2025
| Tower | Updates |
|---|---|
| AURA & ELARA | Aura and Elara towers have received Occupancy Certificate (OC) up to the 35th floor |
| Tower | Updates |
|---|---|
| NOVA |
(Under Construction – Significant Progress Made) |
| Structural Progress:
Slab work is completed up to the 24th floor. |
|
| Interior Work:
Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor. Plumbing & Waterproofing: Installed up to the 23rd floor. Gypsum Work: Completed up to the 23rd floor. Kitchen Platforms: Installed up to the 23rd floor. Flooring: Tiling completed up to the 23rd floor. Doors & Frames: Installed up to the 23rd floor. Fire Safety: Firefighting system work completed up to the 23rd floor. |
|
| External & Infrastructure Work:
Surrounding infrastructure work in Progress. Storm water drainage is 95% complete. Basement & underground facilities (such as water tanks and STP) are fully completed. |
| Tower | Updates |
|---|---|
| FLORA |
(Under Construction – Significant Progress Made) |
| Structural Progress:
Slab work is completed up to the 21st Floor & 22nd slab casting work in progress 10th floor brick work & electric conduit in wall completed Concealed plumbing & waterproofing completed till 6th floor Gypsum work completed till 6th floor Tiling work in progress on first floor Door frame fixing completed till 4th floor. Fire fighting work in progress |
|
| External & Infrastructure Work:
Basement & underground facilities (such as water tanks and STP) are fully completed. Periphery Retaining Wall & Pump Room Construction completed. |