Construction Updates – June 2025

Update as on 9th June, 2025

Construction Updates – June 2025

Update as on 9th June, 2025

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA & ELARA Aura and Elara towers have received Occupancy Certificate (OC) up to the 35th floor
Tower Updates
NOVA

(Under Construction – Significant Progress Made)

Structural Progress:

Slab work is completed up to the 24th floor.

Interior Work:

Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor.

Plumbing & Waterproofing: Installed up to the 23rd floor.

Gypsum Work: Completed up to the 23rd floor.

Kitchen Platforms: Installed up to the 23rd floor.

Flooring: Tiling completed up to the 23rd floor.

Doors & Frames: Installed up to the 23rd floor.

Fire Safety: Firefighting system work completed up to the 23rd floor.

External & Infrastructure Work:

Surrounding infrastructure work in Progress.

Storm water drainage is 95% complete.

Basement & underground facilities (such as water tanks and STP) are fully completed.

Tower Updates
FLORA

(Under Construction – Significant Progress Made)

Structural Progress:

Slab work is completed up to the 7th Floor & 8th floor RCC pour 1 completed and pour 2 will be in progress.

2nd floor brick work & electric conduit in wall completed

External & Infrastructure Work:

Basement & underground facilities (such as water tanks and STP) are fully completed.

Periphery Retaining Wall & Pump Room Construction completed.

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.