Construction Updates – October 2025

Update as on 6th October, 2025

Construction Updates – October 2025

Update as on 6th October, 2025

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA & ELARA Aura and Elara towers have received Occupancy Certificate (OC) up to the 35th floor
Tower Updates
NOVA

(Under Construction – Significant Progress Made)

Structural Progress:

Slab work is completed up to the 24th floor.

Interior Work:

Walls & Finishing: Blockwork and internal plastering are completed up to the 23rd floor.

Plumbing & Waterproofing: Installed up to the 23rd floor.

Gypsum Work: Completed up to the 23rd floor.

Kitchen Platforms: Installed up to the 23rd floor.

Flooring: Tiling completed up to the 23rd floor.

Doors & Frames: Installed up to the 23rd floor.

Fire Safety: Firefighting system work completed up to the 23rd floor.

External & Infrastructure Work:

Surrounding infrastructure work in Progress.

Storm water drainage is 95% complete.

Basement & underground facilities (such as water tanks and STP) are fully completed.

Tower Updates
FLORA

(Under Construction – Significant Progress Made)

Structural Progress:

Slab work is completed up to the 21st Floor & 22nd slab casting work in progress

10th floor brick work & electric conduit in wall completed

Concealed plumbing & waterproofing completed till 6th floor

Gypsum work completed till 6th floor

Tiling work in progress on first floor

Door frame fixing completed till 4th floor.

Fire fighting work in progress

External & Infrastructure Work:

Basement & underground facilities (such as water tanks and STP) are fully completed.

Periphery Retaining Wall & Pump Room Construction completed.