Construction Updates – October 2020.

Aura and Elara
AURA
ELARA
AURA

Completed RCC work upto 21st floor

Detailed updates (Possession – December 2021):
Completed RCC work upto 21st floor , 22nd RCC work in progress (80 % completed)
Blockwork completed till 20th floor
Concealed plumbing work completed upto 15th floor and partially completed till 19th floor
Gypsum work completed upto 15th floor and partially completed till 19th floor
Waterproofing completed upto 15th floor and partially completed till 19th floor
Concealed electrical work in blockwork completed upto 15th Floor
Door Frame fixing work completed upto 4th Floor
Window rough ground marble fixing completed upto 16th Floor
Window sill fixing completed upto 16th floor
Tiling & dado completed till 2nd floor. Partially completed till 10th floor.
Kitchen Platform fixing completed upto 2nd Floor. Partially completed till 15th floor.

ELARA

RCC work 5th floor completed and 6th floor 70% done